A Presentation on
AGGREGATE PRODUCTION PLANNING Presented By : Kausar Hayat Manju Priyanka Vatsh Lipika Roy Kanika Sharma September 23, 2009 Charu SinghSECTION-A
PGDM
4TH TRIMESTER
1
PLANNING Planning is a process of logical thinking or brain storming and outcome of planning is a plan. In industries planning means integration of activities required for conversion of sales SECTION-A PGDM 4TH September 23, 2009 TRIMESTER orders into actual products or
2
Objectives of Planning To meet desired production schedules in terms of quantity, quality and time. Optimum utilization of resources through : Minimizing number of setups Effective in process inventory control(work in progress) Proper material handling system Minimizing idle time of machines and manpower.
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
3
Two Basic Strategies are:APP strategy APP alternatives Key features applicable Level strategy
Inventory based alternatives a)Build inventory b)Backlog /backorder
Inventory as the critical link between the periods; made-tostock environment; products with low risk of obsolescence
Chase strategy
Capacity adjustment alternatives a)Over time/undertime b)Vary no.of shifts c)hire/lay off workers
no inventory carried from one period to another; several service systems
September 23, 2009
Capacity augmentation alternatives:a)subcontract/outsource SECTION-A PGDM b)De-bottleneck 4TH TRIMESTER
4
MIXED STRATEGY This strategy employs a combination of the available alternatives for APP Mixed Strategy 1 : d. hire workers at the beginning of the planning e. maintain a constant production rate f. utilize inventory based alternatives Mixed Strategy 2 : h. do not hire/layoff workers i. adjust the production rates j. use23,inventory and subcontracting to match September 2009 SECTION-A PGDM 4TH 5 TRIMESTER supply /demand
Mixed Strategy 3 : b. do not hire/layoff workers c. use subcontracting during period of high demand and build inventory during low demand.
September 23, 2009
SECTION-A PGDM 4TH TRIMESTER
6
QUESTIONS September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
7
Question 1 • A manufacturer of ceiling fans offer three different versions of the product to its customers: basic(three blades), improved (four blades) and deluxe(enhanced performance features).The table below has information on the machines hours required for each of these variations and the number of fans to be manufactured in the next quarter. Assume 25 working days per month. • Choose an appropriate aggregate unit for planning the production • For the chosen aggregate unit, estimate the capacity required SECTION-A PGDM 4TH • If the September 23, 2009 manufacturer operates two shifts8 TRIMESTER
Solution: Fan type
April
May
June
Basic
140
160
160
M/c hours per unit 9.50
Improve d
110
150
150
12.00
Deluxe
120
120
140
18.50
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
9
Case1:
Basic
April
May
June
140*9.50= 1330
160*9.50= 1520
160*9.50= 1520
Improved
110*12.00= 150*12.00= 150*12.00= 1320 1800 1800
Delux
120*18.50= 120*18.50= 140*18.50= 2220 2220 2590
Total
September 23, 2009
4870
SECTION-A PGDM TRIMESTER
5540
4TH
5910
10
Case 2 : • Estimate the capacity required? Aggregate Capacity= working hours*number of working days = 8*25 = 200 • 4870/200=25 25 machines are required in April. 5540/200=28 28 machines are required in May 5910/200=30 30 machines are required in June SECTION-A PGDM 4TH September 23, 2009 11 TRIMESTER
Case 3 : • Manufacturer operates 2 shifts each of 8 hours i.e. 200+200=400 • 4870/400=13 13 machines are required in April to fulfill the requirement of next quarter. • 5540/400=14 14 machines are required in May • 5910/400=15 15 machines are required in month of SECTION-A PGDM 4TH September 23, 2009 12 TRIMESTER June.
Question 2 A manufacturing organisation employs 220 people in the factory. The Manufacturing is largely manual, therefore, man hours are a good measure of the capacity of the system. The factory currently works on a single shift of 8 hours. The no. of working days for the next 6 months is as follows : 24, 22, 25, 19, 21 and 23. The company uses this information to plan its capacities. SECTION-A PGDM 4TH The demand September 23, 2009 for its product during the next 613 TRIMESTER
Under these circumstances, analyse the situation and answer the following questions: c)What is the total capacity available in the factory as of now? d)The company is considering 3 options to meet the impending demand for capacity v. Introduce 2 hours of overtime for the next 6 months vi. Introduce 1 hour of overtime for the next 6 months vii. Introduce 2hours of overtime for the first 6 months and 2 hours of idle time thereafter. SECTION-A PGDM 4TH September 23, 2009 14 TRIMESTER
Solution (a) : No. of workers
220
Working hours
8
MONT HS 1
WORKI CAPACIT CURREN NG Y T DAYS (HOURS DEMAND ) 24 42240 33792
PROJECTED DEMAND FOR NEXT 6 MONTHS 45619
2
22
38720
30976
41818
3
25
44000
35200
47520
4
19
33440
26752
36115
5
21
36960
29568
39917
6
23
40480
32384
43718
TOTAL CAPACITY
September 23, 2009
235840 SECTION-A PGDM TRIMESTER
4TH
15
Solution (b) : Case (i) 2 hours overtime for the next 6 months : MONT HS
WORKI NG DAYS
EXISTI NG CAPACI TY
CAPACIT Y (OVERTI ME)
7
24
8
22
38720
9
25
10
42240
10560
TOTAL DEMAND CAPACI CAPACI (PROJECT TYDEM TY ED) AND “A” “B” C = A-B
52800
45619
7181
9680
48400
41818
6582
44000
11000
55000
47520
7480
19
33440
8360
41800
36115
5685
11
21
36960
9240
46200
39917
6283
12
23
40480
10120
50600
43718
6882
TOTAL CAPACITY DEMAND
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
40093
16
Solution (b) : Case (ii) 1 hour overtime for the next 6 months : MONT HS
WORKI NG DAYS
EXISTI NG CAPACI TY
CAPACIT Y (OVERTI ME)
7
24
8
22
38720
9
25
10
42240
5280
TOTAL DEMAND CAPACI CAPACI (PROJECT TYDEM TY ED) AND “A” “B” C= A-B
47520
45619
1901
4840
43560
41818
1742
44000
5500
49500
47520
1980
19
33440
4180
37620
36115
1505
11
21
36960
4620
41580
39917
1663
12
23
40480
5060
45540
43718
1822
TOTAL CAPACITY DEMAND
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
10613
17
Solution (b) : Case (iii) 2 hours of overtime for the first 3 months & 2 hours of idle time thereafter : MONT HS
WORKI NG DAYS
EXISTI NG CAPACI TY
CAPACIT Y CHANGE (OT/UT)
7
24
8
22
38720
9
25
10
42240
10560
TOTAL DEMAND CAPACI CAPACI (PROJECT TYDEM TY ED) AND “A” “B” C= A-B
52800
45619
7181
9680
48400
41818
6582
44000
11000
55000
47520
7480
19
33440
(8360)
25080
36115
11
21
36960
(9240)
27720
39917
12
23
40480
(10120)
30360
43718
(11035 ) (12197 ) (13358 ) (1534 7)
TOTAL CAPACITY DEMAND September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
18
Question 3 Suppose in the above problem, the following are the costs pertaining to overtime, inventory and shortage and idle time:(d)Overtime premium:Rs.4.00 per hour. (e)Idle time costs :Rs.2.00 per hour. (c) Cost of holding inventory :Rs.10.00 SECTION-A PGDM 4TH September 23, 2009 19 per hour. TRIMESTER
Case 1 : Two hour Overtime for next six months
Month Openin Closin Inventor OT/U s g g y T Invent Invent /Shorta hours ory ory ge Cost 7 0 7180 35904 10560
OT/UT Cost
Total Cost
42240
78144
8
7180
13763
104720
9680
38720
143440
9
13763
21243
175032
11000
44000
219032
10
21243
26928
240856
8360
33400
274296
11
26928
33211
300696
9240
36960
337656
12
33211
40092
366520
10120
40480
407000
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
20
Case2 : One hour Overtime for next six months
Month s 7
Openin Closing Invent g Invent ory Invent ory /Shorta ory ge 0 1900 9504 Cost
OT/UT hours
OT/UT Cost
Total Cost
5280
21120
30624
8
1900
3643
27720
4840
19360
47080
9
3643
5623
46332
5500
22000
68332
10
5623
7128
63756
4180
16720
80476
11
7128
8791
79596
4620
18480
98076
12
8791
10612
97020
5060
20240
117260
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
21
Case 3 : Two hours OT for next three months, two hours under time thereafter Month s 7
Openin g Invent ory 0
Closin g Invent ory 7180
OT/UT hours
OT/UT Cost
Total Cost
10560
42240
78144
13763
Invent ory /Short age 35904 Cost 104720
8
7180
9680
38720
143440
9
13763
21243
175032
11000
44000
219032
10
21243
10208
157256
(8360)
16720
173976
11
10208
-1988
90800
(9240)
18480
109280
12
0
-15347
20240
327180
September 23, 2009
306940 (10120)
SECTION-A PGDM TRIMESTER
4TH
22
Question 4 Hot spot is a fast food restaurant located in a prominent locality in the city of Bangalore. Hot spot offers three different menus of breakfast : standard, extended, custom made. The standard offering takes nearly 20 minutes of one worker and the extended requires 30 minutes. On the other hand, custom made requires three workers to spend 25 minutes each. SECTION-A PGDM 4TH September 23, 2009 TRIMESTER
23
Type of service offered
Demand during next 4 weeks
STANDA RD
1
2000
2
3
2200
4
2500 2800
1700
1600
1000
EXTEND ED
1300 500
600
400 200
CUSTOM -MADE September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
24
Solution: DEMAND DURING WEEKS
Type of service offered STANDA RD EXTEND ED CUSTOM -MADE
1
2
3
In units
4
Number of workers 1
2000
1700
220 0 1 600
500
600
September 23, 2009
std time (mins) per worker 20
2800 2500 1300
1
30
3
25
1000 200
400
SECTION-A PGDM TRIMESTER
4TH
25
No. of hours taken by worker: For standard : 20/60*1 = 0.33 For extended : 30/60*1 = 0.5 For custom–made : 25/60*3 = 1.25
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
26
In hours CUSTOMMADE
WEEKS STANDARD EXTENDED 1
2
660
726
3
924
4
825
850
800 650 500
625
750 250 500
CAPACITY/ DEMAND(h rs) (TOTAL) 2135
2276 1824 1825
Question 5 Assume that hot spot currently employs 29 workers in its restaurant. If hot spot works for 6 days a week, 10 hrs a day compute the following: (c)What is capacity available at hot spot in its current level of working? (d)Is the capacity adequate to meet the demand? If not, how much additional capacity do they need? (e)What alternatives would you recommend to hot spot to solve their capacity problem?
Given: No. of employees – 29 Work schedule – 10 hrs a day Work week – 6 days
Available/current capacity= no. of working days * working hrs* no. of worker = 6* 29 * 10 = 1740 Demand(hrs)
Addl. capacity
2135
Available capacity (hrs) 1740
2276
1740
536
1824
1740
84
1825
1740
85
395
(a) Current capacity is 1740 hrs per week. (b) No, the current capacity is inadequate. Additional capacity needed is shown above. (c) Alternatives available: 4.To maintain flexible workforce through hire/fire. 5. To recruit average no. of workers and manage additional requirement through hiring temporary workers. 6. To recruit peak load requirement and investigate method for increasing
(d) No. of employee to be hire = shortage/working hr.* no. of working days Hire For 1st week = 395/6*10 = 6.58 or 7 Hire For 2nd week = 536/6*10 = 8.93 or 9 Hire For 3rd week = 84/6*10 = 1.40 or 2 Hire For 4th week = 85/6*10 = 1.42 or 2 Additional capacity
Man hrs
Week 1
395
No. of employees to be hire 7
Week 2
536
9
Week 3
84
2
Week 4
85
2
Example 11.4 A manufacturer of industrial motors produces four varieties of motors. Type 4 motor requires a greater amount of customization than the other three. The production planning department has estimated the no of hours required for manufacturing one unit of motor of each PGDM 4TH variety. typeSECTION-A 1 requires 125 hrs ; September 23, 2009 32 TRIMESTER
Forecast of
Motor Demand
In units
Months
Type1
Type2
Type3
Type4
April
100
40
60
10
May
90
30
30
5
June
80
50
50
10
July
130
40
70
20
August
70
30
30
15
Septembe r October
90
50
50
5
100
40
50
10
Novembe r December
110
30
40
15
60
60
80
5
January
110
20
30
10
February
120
40
40
5
March
140
50
70
10
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
33
Contd…….. Overtime premium is estimated to be Rs 20/hr while under time costs are 50% of OT premium. the cost carrying inventory is Rs 15/hr/mnth and the backordering/shortage costs are 200% of the inventory carrying costs. The company can sub-contract capacity from a reputed vendor and the additional costs related to subcontracting is Rs 25/hr of the capacity. Evaluate the following alternatives SECTION-A PGDM 4TH for APP: September 23, 2009 34 TRIMESTER
Contd…….. (b) Use constant production rate for the first six months, change the production rate to another level and have a constant production rate for the next six months. use inventory/backlogging to absorb demand-supply mismatch. (c) Maintain a production level of 31,000 hrs/month and use OT/UT alternatives to chase the demand. (d) Maintain a production level of 31,000hrs/month. Build inventory during periods of low demand and use subcontractingSECTION-A when the exceeds 35 PGDMdemand 4TH September 23, 2009 TRIMESTER available capacity.
Aggregate of Product Demand:
hr/uni t
125
175
200
350
Forecast of Motor Demand (units)
Forecast of Motor Demand (hrs)
Mont Type Type Type Type4 Type Type Type Type Total h 1 2 3 1 2 3 4 April 100 40 60 10 1250 7,000 12,00 3,500 35,00 0 0 0 May 90 30 30 5 1125 5,250 6,000 1,750 24,25 0 0 June 80 50 50 10 10,00 8,750 10,00 3,500 32,25 July
130
40
70
20
Aug
70
30
30
15
Sep
90
50
50
5
Oct
100
40
50
10
Nov
110
30
40
15
Dec
60
60
80
5
Jan
110
20
30
10
Feb
120
40
Marc h
140
50
September 23, 2009
0 0 0 16,25 7,000 14,00 7,000 44,25 0 0 0 8,750 5,250 6,000 5,250 25,25 0 11,25 8,750 10,00 1,750 31,75 0 0 0 12,50 7,000 10,00 3,500 33,00 0 0 0 13,75 5,250 8,000 5,250 32,25 0 0 7,500 10,50 16,00 1,750 35,75 0 0 0 13,75 3,500 6,000 3,500 26,75
0 0 15,00 7,000 8,000 1,750 31,75 0 0 70 10 17,50 8,750 14,00 3,500 43,75 0 0 SECTION-A PGDM 0 4TH 40
5
TRIMESTER
36
Plan A-Level Strategy Months
Prd rate(hr) 33,000
Prodct dmd (2000)
Opng invt 0
Closng invt (2000)
C.o.I/B.O
April
Demand (hr 35,000
May
24,250
33,000
8,750
(2000)
6,750
50,625
June
32,250
33,000
750
6,750
7,500
1,06,875
July
44,250
33,000
(11,250)
7,500
(3,750)
1,68,750
Aug
25,250
33,000
7,750
(3,750)
4,000
30,000
Sep
31,750
33,000
1,250
4,000
5,250
69,375
Oct
33,000
33,000
0
5,250
5,250
78,750
Nov
32,250
33,000
750
5,250
6,000
84,375
Dec
35,750
33,000
(2,750)
6,000
3,250
69,375
Jan
26,750
33,000
6,250
3,250
9,500
95,625
Feb
31,750
33,000
1,250
9,500
10,750
151,875
March
43,750
33,000
(10,750)
10,750
0
80,625
Avg. (12)
33,000
September 23, 2009
Total cost of Plan SECTION-A PGDM TRIMESTER
4TH
60,000
10,46,25 0 37
Calculations: Cost of inventory = Rs 15/hr/month Cost of shortage/backlogging=200% * 15=Rs 30 Months
Cost of inventory/cost of shortage
April
2000*30= Rs60,000
May
6750/2*15= Rs 50,625
June
(6750+7500)/2*15 = Rs 1,06,875
July
(7500/2)*15 +3750*30 = Rs 1,68,750
August
(4000/2)*15 =Rs 30,000
Sep
(4000+5250)/2*15 =Rs 69,375
Oct
(5250+5250)/2*15 = Rs 78,750
Nov
(5250+6000)/2*15 = Rs 84,375
Dec
(6000+3250)/2*15 = Rs 69,375
Jan
(3250+9500)/2*15 = Rs 95,625
Feb
(9500+10750)/2*15 = Rs 151,875
March
(10750/2)*15 = Rs 80,625
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
38
Plan B-two level of Constant Production Months Demand Prd Rate Prd Opng Clsng C.O.I/C. (h
rate(hr)
dmd
invt
invt
B.O
April
35,000
32,125
(2,875)
0
(2,875)
86,250
May
24,250
32,125
7,875
2,875
5,000
37,500
June
32,250
32,125
(125)
5,000
4,875
74,063
July
44,250
32,125
4,875
(7,250)
2,54,063
August
25,250
32,125
(12,125 ) 6,875
(7,250)
(375)
11,250
Sep
31,750
32,125
375
(375)
0
----
Oct
33,000
33,875
875
0
875
6,563
Nov
32,250
33,875
1,625
875
2,500
25,313
Dec
35,750
33,875
(1,875)
2,500
625
23,438
Jan
26,750
33,875
7,125
625
7,750
62,813
Feb
31,750
33,875
2,125
7,750
9,875
1,32,188
March
43,750
33,875
(9,875)
9,875
0
74,063
Avg(fst 6) Avg(sec
32,125 33,875
September 23, 2009 6)
Total cost Of the plan SECTION-A PGDM TRIMESTER
4TH
7,87500 39
Plan C: Chase Strategy with OT/UT Mont h April
Dema nd (hrs) 35,000
Prod Rate (hrs) 31,000
Prod. Demand (hrs) (4,000)
Op. Invent (hrs) 0
Clg. Invent (hrs) 0
Cost of OT/UT 80,000
May
24,250
31,000
6,750
0
0
67,500
June
32,250
31,000
(1,250)
0
0
25,000
July
44,250
31,000
(13,250)
0
0
August
25,250
31,000
5,750
0
0
2,65,0 00 57,500
Sept.
31,750
31,000
(750)
0
0
15,000
Octob er Nov.
33,000
31,000
(2,000)
0
0
40,000
32,250
31,000
(1,250)
0
0
25,000
Dec.
35,750
31,000
(4,750)
0
0
95,000
Jan.
26.750
31,000
4,250
0
0
42,500
Feb.
31,750
31,000
(750)
0
0
15,000
March
43,750
31,000
(12,750)
0
0
2,55,0 00 9,82,5
Total cost of the Plan September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
00 40
Plan D: Mixed Strategy Month
Dema nd (hrs)
Prod Rate (hrs)
Prod Demand (hrs)
Op. Inven t (hrs) 0
Clg. Inven t (hrs) (4,000
April
35,000
31,000
(4000)
May
24,250
31,000
6,750
) 2,750
(1,250)
(4,000 ) 2,750
June
32,250
31,000
July
44,250
31,000
(13,250)
1,500
25,250
31,000
5,750
Sept.
31,750
31,000
(750)
(11,75 0) (6,000
(11,75 0) (6,000
August October
33,000
31,000
(2,000)
Nov.
32,250
31,000
(1,250)
Dec.
35,750
31,000
(4,750)
Jan.
26,750
31,000
4,250
Feb.
31,750
31,000
(750)
March
43,750
31,000
(12,750)
Total cost of plan September 23, 2009
SECTION-A PGDM TRIMESTER
) (6,750 ) (8,750 ) (10,00 0) (14,75 0) (10,50 0) (11,25
Cost of the plan
1,500
) (6,750 ) (8,750 ) (10,00 0) (14,75 0) (10,50 0) (11,25 0) 0
0) 4TH
41
September 23, 2009
SECTION-A PGDM TRIMESTER
4TH
42