Project Lakshya1000

Materials Management User Manual

Purchase Requisition (PR): a. Create Purchase Requisition: ME51N b. Change Purchase Requisition: ME52N C. Display Purchase Requisition: ME53N

To Start with Choose Correct document type.

Wipro InfoTech

User Manual – MM

Page 1 of 7

Project Lakshya1000

Materials Management User Manual

1) For material PR – Provide Material, Qty, Delivery Date, Plant, Storage Location, Purchase Group and Requisitioner. 2) For Service PR – Short text, Delivery Date, Material Group, Plant, Purchase Group and Requisitioner

Enter Material, Plant Qty and other relevant data. Note: PR can be created either manually or through MRP. The Creation indicator (manually/MRP) can be known in Contact person tab.

Wipro InfoTech

User Manual – MM

Page 2 of 7

Project Lakshya1000

Materials Management User Manual

Click on Check button to verify the transaction.

Wipro InfoTech

User Manual – MM

Page 3 of 7

Project Lakshya1000

Materials Management User Manual

Delivery address can be seen here (Plant address).

Wipro InfoTech

User Manual – MM

Page 4 of 7

Project Lakshya1000

Materials Management User Manual

1) Update details as shown in Screen. 2) Use item category L for Subcontracting, & D for service & blank for materials

Account Assignment Category: Account assignment has to be used for Non Stock Materials/Consumption materials procurement. Depending on the assignment, you have to enter the respective field. E.g.: for account assignment K, Cost center is mandatory.

Wipro InfoTech

User Manual – MM

Page 5 of 7

Project Lakshya1000

Materials Management User Manual

Item Category: Item Category represents Special Procurement. E.g.:

- Standard L - Represents subcontracting. For L system explodes BOM Automatically. D – Service

Wipro InfoTech

User Manual – MM

Page 6 of 7

Project Lakshya1000

Materials Management User Manual

Click on Save to Post PR. PR Created.

Wipro InfoTech

User Manual – MM

Page 7 of 7