0 Memoria Descriptiva_castrillejo_rev D.docx

  • Uploaded by: Orlando Valverde
  • 0
  • 0
  • May 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View 0 Memoria Descriptiva_castrillejo_rev D.docx as PDF for free.

More details

  • Words: 14,003
  • Pages: 63
INDICE 1. MEMORIA DESCRIPTIVA..................................................................................................................... 4 1.1 NOMBRE DEL PROYECTO........................................................................................................................... 4 1.2 INTRODUCCIÓN ....................................................................................................................................... 4 1.2.1 Antecedentes .............................................................................................................................. 4 1.3 OBJETIVOS ............................................................................................................................................. 5 1.4 METAS FÍSICAS ....................................................................................................................................... 5 1.5 UBICACIÓN DEL PROYECTO ........................................................................................................................ 6 1.6 BENEFICIOS – BENEFICIARIOS DEL PROYECTO ................................................................................................ 8 1.7 RESUMEN DEL COSTOS DEL PROYECTO ......................................................................................................... 8 1.8 PLAZO DE EJECUCIÓN Y ÉPOCA RECOMENDABLE ............................................................................................. 9 1.9 PROCESO CONSTRUCTIVO DE LA OBRA ......................................................................................................... 9 1.9.1 OBJETIVOS ................................................................................................................................... 9 1.9.2 MATERIALES DE CONSTRUCCIÓN ................................................................................................ 9 1.9.3 DESCRIPCION DE LAS OBRAS ....................................................................................................... 9 1.9.3.1. OBRAS PROVISIONALES ...................................................................................................................... 9 1.9.3.2. TRABAJOS PRELIMINARES ................................................................................................................. 10 1.9.3.3. MOVIMIENTO DE TIERRAS ................................................................................................................ 10 1.9.3.4. OBRAS DE CONCRETO SIMPLE .......................................................................................................... 11 1.9.3.5. OBRAS DE CONCRETO ARMADO ....................................................................................................... 12 1.9.3.6. ENCOFRADO Y DESENCOFRADO ....................................................................................................... 12 1.9.3.7. CARPINTERÍA METÁLICA ................................................................................................................... 13

1.10 MODALIDAD DE EJECUCIÓN ................................................................................................................... 13 2. SITUACIÓN ACTUAL.......................................................................................................................... 15 2.1 CARACTERÍSTICAS .................................................................................................................................. 15 2.1.1 Clima ......................................................................................................................................... 15 2.1.2 Precipitación ............................................................................................................................. 15 2.1.3 Temperatura ............................................................................................................................. 15 2.2 VÍAS DE ACCESO Y MEDIOS DE TRANSPORTE ................................................................................................ 15 2.3 UBICACIÓN DE CANTERAS DE AGREGADOS Y RELLENOS .................................................................................. 16 2.4 SITUACIÓN ACTUAL DE LA INFRAESTRUCTURA EXISTENTE................................................................................ 16 3. INGENIERIA DEL PROYECTO ............................................................................................................. 18 3.1 PLANTEAMIENTO HIDRÁULICO: ................................................................................................................ 18 3.1.1 Planificación física..................................................................................................................... 18 3.1.2 Dimensionamiento y cálculos justificatorios ............................................................................. 18 3.2 METAS FISICAS ..................................................................................................................................... 23 3.3 PRESUPUESTO DE OBRA .......................................................................................................................... 24 3.4 COTIZACION DE LOS INSUMOS MAS INCIDENTES ........................................................................................... 25 3.5 PLANILLA DE METRADOS ......................................................................................................................... 26 3.6 RELACION DE MATERIALES E INSIMOS ........................................................................................................ 32 3.7 CALCULO DE FLETE URBANO Y RURAL ......................................................................................................... 33 3.8 FORMULA POLINOMICA .......................................................................................................................... 33 3.9 DESAGREGADO DE GASTOS GENERALES ...................................................................................................... 34 3.10 ESPECIFICACIONES TÉCNICAS .................................................................................................................. 34 3.11 CRONOGRAMA DE EJECUCIÓN DE OBRA .................................................................................................... 52 3.12 CRONGRAMA VALIRIZADO DE OBRA ......................................................................................................... 53 3.13 PLANOS A NIVEL CONSTRUCTIVO ............................................................................................................. 53 4. CONCLUSIONES Y RECOMENDACIONES............................................................................................ 55 5. ANEXOS ........................................................................................................................................... 57 5.1 TOPOGRAFIA DEL AREA DE LAS OBRAS ............................................................................................. 58 5.2 ESTUDIO HIDROLOGICO ................................................................................................................... 59 5.3 DISEÑO HIDRAULICO ........................................................................................................................ 60 5.4 GEOTECNIA PARA DISEÑO DE CIMENTACION ................................................................................... 61 5.5 ANALISIS DE RIESGO DE DESASTRES ................................................................................................. 62 5.6 IDENTIFICACION DE LOS IMPACTOS AMBIENTALES .......................................................................... 63

CAPITULO I: MEMORIA DESCRIPTIVA

1. MEMORIA DESCRIPTIVA 1.1 Nombre del Proyecto REHABILITACION DE LA BOCATOMA CASTRILLEJO, Distrito de Chaclacayo, provincia de Lima, departamento de Lima

1.2 Introducción 1.2.1 Antecedentes Durante el verano del 2017, nuestro país fue duramente golpeado por el Fenómeno El Niño Costero, condición climática producida por el calentamiento anómalo del mar debido al debilitamiento de las corrientes de aire frías, que recorren de sur a norte las costas del Pacífico Sur. Este suceso hizo que ingresen con mayor intensidad los vientos cálidos provenientes del Ecuador, lo que originó el calentamiento inusual de la franja costera del mar. A su vez, los altos niveles de humedad generados desencadenaron lluvias intensas y la crecida de los principales ríos de la vertiente del Pacífico, produciendo desbordes e inundaciones, principalmente en el norte del país. Esta anomalía climática difirió de un Fenómeno El Niño habitual, dado que éste fue un evento climático local, focalizado en las costas de Perú y Ecuador. La zona de impacto de El Niño Costero se extendió por más de la mitad de la costa del Perú, abarcando los departamentos de Tumbes, Piura, Lambayeque, La Libertad, Áncash, Lima e Ica, y ocasionó también movimientos de masas (huaicos, derrumbes y deslizamientos) de gran intensidad en los departamentos de Cajamarca, Ayacucho, Arequipa, Huancavelica, Junín y Loreto. Al ser usuales las lluvias en estas últimas seis regiones, no causaron los daños extremos que sí se registraron en la zona costera. Con el fin de liderar los esfuerzos de la reconstrucción con cambios, en mayo del 2017, el Congreso aprobó el Proyecto de Ley N° 1249-2016-PE enviado por el Ejecutivo, el mismo que establece un régimen normativo excepcional orientado a facilitar la coordinación entre los distintos niveles de gobierno, y expeditar la ejecución de las obras con la finalidad de restituir el bienestar perdido a los ciudadanos. Con la emisión de la Ley N° 30556 se establece la Autoridad para la Reconstrucción con Cambios (RCC), cuya misión principal es liderar el diseño, ejecución y supervisión de un plan integral para la rehabilitación, reposición, reconstrucción y construcción de la infraestructura de uso público comprometida como consecuencia de El Niño Costero. Como se ha señalado, la RCC tiene como una de sus principales responsabilidades la preparación del Plan Integral de Reconstrucción con Cambios (PIRCC), el mismo que se ha elaborado tomando como insumo principal el catastro de daños reportados por los sectores estatales, luego de revisar, compilar y sistematizar la información alcanzada por el Instituto Nacional de Defensa Civil (INDECI), los municipios y gobiernos regionales. El Plan Integral identifica las obras e iniciativas que serán implementadas, indicando además la instancia responsable de su ejecución y aquella encargada de recibir las obras para su mantenimiento y operación, así como la modalidad de inversión que

será utilizada para su ejecución (incluyendo el mecanismo de Obras por Impuestos). Una vez formulado, el plan será remitido en consulta a las autoridades locales y regionales, luego de lo cual la RCC lo procederá a enviarlo al Consejo de Ministros para su aprobación. La Reconstrucción con Cambios implicará la inversión de 2,180 millones de soles en la región de Lima. Este total equivale a cerca del 10% del Producto Bruto Interno de Lima Provincias y permitirá la creación de 13,000 nuevos puestos de trabajo, cifra de casi tres veces el empleo que se genera en promedio por año en la región. Gran parte de la inversión estará enfocada en solucionar la raíz del problema: obras de control de inundaciones en la quebrada Huaycoloro, además de los ríos Rímac, Mala, Huaura y Cañete. En el distrito de Chaclacayo dentro portafolios del Plan Integral de Reconstrucción con Cambios se han considerado seis proyectos del sector agricultura (Rehabilitación de Bocatomas y Canales), las mismas que han perdido su capacidad de captación y conducción de agua hacia los terrenos de cultivo del sector Castrillejo. El presente proyecto es elaboración de los documentos técnicos REHABILITACION DE LA BOCATOMA CASTRILLEJO, Distrito de Chaclacayo, provincia de Lima, departamento de Lima, comprendida en el PIRCC.

1.3 Objetivos El objetivo es recuperar la capacidad de captación de agua de la bocatoma Castrillejo, que a sufrido daños por las aguas de las máximas avenidas del rio Rímac durante el Fenómeno El Niño Costero del 2017, para restablecer el servicio de abastecimiento de agua para riego que brindaba la bocatoma.

1.4 Metas Físicas  



 

Construccion de 10m de Canal de conducción y 2m de canal de canal de limpia en concreto simple f´c = 175 Kg/cm2. 03 Muros de protección aguas abajo y aguas arriba de concreto armado f´c=280 Kg/cm2, cuya altura de cimentación es de 1.80m y la altura de la pantalla es de 2.80m. 01 muro de Mamposteria de piedra asentada f´c =175 Kg/cm2, como protección de muros y pisos, cuya altura de cimentación es de 2.55m y la altura de cimentación es de 1.30m. 03 Columnas y 01 Losa de maniobra de concreto armado f´c=210 kg/cm2. Las columnas tiene una altura de cimentación de 0.60 y altura de pantalla 2.40m. 02 Carpinterias metálicas de 0.80mx1.20m y 1.0mx1.20m, respectivamente.

1.5 Ubicación del Proyecto Política: Región

: Lima

Provincia

: Lima

Distrito

: Chaclacayo

Sector

:2

Geográfica: Coordenadas UTM: Este

: 304211

Norte

: 8674907

Altitud

: 608 m.s.n.m.

Límites: Sus límites distritales son los siguientes: Por el Norte:

Con el distrito de Lurigancho-Chosica y con el rio Rímac, en su recorrido distrital

Por el Sur:

Con los distritos de Cieneguilla y con las altas cumbres de los cerros rocosos que corren paralelos al rio Rímac

Por el Este:

Con los distritos de Lurigancho y con la villa de los ángeles y el fundo Yanacoto (Distrito de Chosica)

Por el Oeste:

Con el distrito de Ate-Vitarte

Administración y manejo del agua con fines agrícolas: Comisión de Usuarios

: La Estrella

Junta de Usuarios

: Sector Hidráulico Rímac

ALA

: Chillón-Rímac-Lurín

Figura N° 1: Ubicación nacional, departamental y regional del proyecto

Ubicación Departamental del Proyecto

Ubicación Provincial del Proyecto

Ubicación Distrital del Proyecto

Chaclacayo

1.6 Beneficios – Beneficiarios del proyecto El beneficio directo del presente proyecto es la recuperación de la capacidad de captación de la bocatoma Castrillejo. Los beneficiarios directos son los 22 integrantes de la Comision La Estrella que en total tienen una superficie bajo riego de 29.02 ha. Tabla N° 1: Relación de beneficiarios de canal derivador Castrillejo SUPERFICIE (Ha.)

N° ORD

1 2 3 4 5 6 7 8 9 10

N° REG. JUR

APELLIDOS Y NOMBRE

Castrillejo D1 (Tomas directas) MUNICIPALIDAD DISTRITAL DE CHACLACAYO 50545 CANESILLAS ROJAS ZENOBIO 50111 HERMOSA PUMAHUACRE EVARISTA 50513 CENTRO CULTURAL PERUANO CHINO 50123 CENTRO CULTURAL PERUANO CHINO 50544 COM. URB. AUTOGESTIONARIA DE HUAYCAN 50485 FRANCISCANOS COLONIA CHINA PARA EL PERU 50296 LAGUNA ARONI MARGARITA 50184 SUC. INT. SACRAMENTO ESPINOZA CONCEPCION 50297 ASOCIACIÓN AGRARIA CERRO EL ÁNGEL 50561 TOTAL PARCIAL

Total

Bajo Riego

6.3600 0.5000 0.5000 9.5000 2.5000 1.0000 1.5000 0.5000 2.5000 4.0000 28.86

6.3600 0.5000 0.5000 9.5000 2.5000 1.0000 1.5000 0.5000 0.5000 4.0000 26.86

0.0000 0.0000 0.0000 9.5000 2.5000 1.0000 1.5000 0.0000 0.0000 0.0000 14.50

6.3600 0.5000 0.5000 0.0000 0.0000 0.0000 0.0000 0.5000 0.5000 4.0000 12.36

0.6500 0.2800 0.2500 0.0800 1.26

0.2850 0.2800 0.2500 0.0800 0.90

0.0000 0.0000 0.0000 0.0000 0.00

0.2850 0.2800 0.2500 0.0800 0.90

Licencia

Por Regul.

Religiosas L1 1 2 3 4

50433 50432 50434 50435

VICARIATO APOSTÓLICO DE SAN RAMÓN ASOC. RENOVACIÓN CARISMÁTICA CATÓLICA - PERÚ DE LOS RÍOS DELGADO BLANCA ISABEL MORALES YÁÑEZ Y OTROS MARTHA TOTAL PARCIAL

Descanso Alto L1 1 2 3

50564

CASTAÑEDA HINOSTROZA SINFOROSA AMELIA

0.1000

0.1000

0.0000

0.1000

50554 50556

TORRES CHAMORRO JOSE CARLOS

0.0200 0.1500 0.27

0.0200 0.1500 0.27

0.0000 0.0000 0.00

0.0200 0.1500 0.27

0.0100 0.0300 0.04

0.0100 0.0300 0.04

0.0000 0.0000 0.00

0.0100 0.0300 0.04

TOTAL PARCIAL

0.20 0.50 0.25 0.95

0.20 0.50 0.25 0.95

0.00 0.00 0.00 0.00

0.20 0.50 0.25 0.95

TOTAL GENERAL

31.38

29.02

14.50

14.52

RIOS MARQUEZ OSCAR ALEJANDRO TOTAL PARCIAL

Santiago L2

1 2

50559 50460

SANTIAGO MORAN JUAN IGNACIO ASIS ANGELES MAURO ESTEBAN TOTAL PARCIAL

Misioneros L2

1 2 3

50565 50552 50558

ASOC. RELIGIOSA MISIONEROS MONFORTIANOS ZIGHELBOIM KLEIN ANTONIO ERICH AÑAÑOS CASTILLA GLICERIO

1.7 Resumen del costos del proyecto COSTO DIRECTO GASTOS GENERALES UTILIDAD SUB TOTAL IMPUESTO GENERAL A LAS VENTAS. IGV (18%) COSTO DE OBRA GASTOS DE SUPERVICION PRESUPUESTO TOTAL DE OBRA

222,592.74 20,255.79 23,691.16 266,539.69 47,977.14 314,516.84 22,500.00

337,016.84

1.8 Plazo de ejecución y época recomendable El plazo de ejecución será de 90 dias calendarios y la época mas recomendable para la ejecución de la obra son durante los meses de abril a setiembre.

1.9 Proceso constructivo de la obra 1.9.1 OBJETIVOS Rehabilitacion de la Bocatoma Castrillejo. Canal de conducción y canal de limpia Muros de protección aguas abajo y aguas arriba de concreto armado f´c=280 Kg/cm2 Mamposteria de piedra asentada como protección de muros y pisos Columnas y Losa de maniobra de concreto armado f´c=210 kg/cm2. Carpinteria metalica (02 compuertas metálicas) 1.9.2 MATERIALES DE CONSTRUCCIÓN Los materiales de agregados los ubicamos en el lecho del río Rimac habiéndose sectorizado dentro del perímetro de la Bocatoma, ubicando bancos de material fino. Geológicamente corresponden a depósitos fluvio aluviales constituidos por mezcla de gravas con arenas, mal graduadas y limpias de naturaleza principalmente intrusiva y volcánica de bordes sub angulares y sub redondeados con inclusiones de cantos y bloques en un 10% a 15%, estimando una pérdida por durabilidad menor del 5%. Las características físicas de los materiales son favorables para ser usados como agregados finos y gruesos debiéndose tamizar y definir la granulometría para el diseño del concreto, en la etapa de ejecución de obra. Los volúmenes para la explotación superan los requerimientos para la construcción de las obras proyectadas. En la fabricación de los agregados se utilizaron 2 mallas de fierro corrugado, una para zarandear el hormigón fino y la otra para separar la arena de la piedra. Sin embargo, se coordinará con la Supervisión de obra en realizar los diseños de mezclas correspondientes para la utilización del hormigón zarandeado, puesto que este hormigón presentaba una equidad de arena y piedra accesible para la fabricación del concreto. Las mallas se colocaran en los lugares que presentaban bancos finos de material de río. 1.9.3 DESCRIPCION DE LAS OBRAS 1.9.3.1. OBRAS PROVISIONALES Con el fin de hacer partícipe a la población, sea residente del lugar o de tránsito temporal, que se está ejecutando una obra por encargo de una Entidad Estatal, se

confeccionó un Cartel de Obra que presentaba las siguientes medidas: 2,40m de ancho x 3,60m de altura. 1.9.3.2. TRABAJOS PRELIMINARES Todas las obras serán construidas de acuerdo con los trazos, gradientes y dimensiones mostradas en los planos originales, complementados o modificados por el diseñador. La responsabilidad completa por el mantenimiento de lineamiento y gradientes de diseño, recae sobre el ingeniero jefe de proyecto. Los alineamientos y gradientes serán dispuestos por el ingeniero Residente según el progreso de la obra, previa coordinación con la Supervisión de obra, y estarán localizados de acuerdo a la topografía del terreno, tratando de causar el menor inconveniente. Para la realización de los trazos y comprobación de las marcas de gradiente, se establecerán puntos de nivel desde un hito cerca de la Bocatoma, se tomaron líneas de base y otros puntos principales de control. 1.9.3.2.1 Movilización y Desmovilización de Equipo Para dar inicio a la ejecución de las obras, se debe suministrar y transportar al lugar de la obra el equipo mecánico necesario para iniciar la obra de reconstrucción. Por consiguiente, la movilización y desmovilización de equipos incluye el costo de manipuleo, almacenamiento, mano de obra, etc. para transportar el equipo mecánico al lugar de la obra. Siendo dentro del costo a calcularse el equipo que puede transportarse por sus propios medios (volquetes) y el equipo que requiere ser trasportado en camiones plataformas (p.e. cargadores frontales, retroexcavadora, tractor de oruga, mezcladora de concreto, rodillos vibratorias, etc.). La partida incluye además la desmovilización del equipo al concluir la obra. 1.9.3.3. MOVIMIENTO DE TIERRAS 1.9.3.3.1 Desvío provisional del Río Una de las partidas más complicadas de realizar durante la 1° etapa de la obra. Comprende los trabajos correspondientes a lograr el desvío del río y facilitar la ejecución de las obras, para lo cual se procederá a trasladar el material propio del lecho del río, mediante tractor D7, para formar diques que cierren el cauce hacia la Bocatoma, así como realizar las zanjas necesarias para encauzar las aguas hacia las zonas que no afecten el normal desarrollo de los trabajos. 1.9.3.3.2 Excavacion en material conglomerado Estas excavaciones se realizaron para conformar las secciones de los canales y compuertas, así como para cimentar o alojar las estructuras de acuerdo con los alineamientos, perfiles y secciones señalados en los planos, esto se realizará con la finalidad de lograr limpieza y un adecuado trabajo topográfico, logrando descolmatar el terreno hasta la cota indicada en los planos.

1.9.3.3.3 Excavacion en materail conglomerado bajo agua El mismo concepto de excavaciones masivas pero esta vez realizada exclusivamente con Retroexcavadoras. Estas excavaciones se realizaron en las cimentaciones de las estructuras de la misma Bocatoma y el enrocado. 1.9.3.4. OBRAS DE CONCRETO SIMPLE 1.9.3.4.1 Materiales a) Cemento El cemento a emplearse en la preparación del concreto fue el Cemento Portland tipo I, el cual cumple con los requisitos establecidos en la norma ASTMC-150. El Cemento será almacenado en obra en un lugar seco y protegido contra la humedad. b) Agregados Se entiende por agregado fino a aquella parte de los agregados que pasa la malla Nº 4 (4,76mm) y es retenido en la malla No. 200 (0,074mm) de graduación U.S. Standard. De acuerdo a las Especificaciones Técnicas, el agregado fino consiste en arena natural constituida por partículas duras, resistentes, sin exceso de formas planas, exentos de polvo y suciedad. Los bancos de material fino localizados en el lecho del río Rimac, a escasos metros de la zona de obra, serán autorizados por el Ingeniero Supervisor para ser utilizados, de acuerdo a la granulometría, como agregados para la fabricación del concreto. Se entiende por agregado grueso a aquella parte de los agregados que no pasa la malla No 4 (4,76mm). De acuerdo a las Especificaciones Técnicas, los agregados gruesos presentan fragmentos duros resistentes, compactados, sin escamas, exentos de polvo y materia orgánica en general y deberá estar de acuerdo con las normas ASTM C-33. Las especificaciones técnicas exigen que los agregados gruesos no excedan los siguientes valores: Prueba de abrasión tipo Los Ángeles (ASTM C-131), si la pérdida usando la graduación estándar (Tipo A) supera el 10% en peso para 100 revoluciones o 40% en peso para 500 revoluciones. Resistencia a la acción del sulfato de sodio (ASTM C-88) si la pérdida de medida en peso, después de 5 ciclos supera el 14%.

Peso específico, si el peso específico del material (en estado de saturación con superficie seca) es inferior a 2,58g/cm2 (ASTM C-127). 1.9.3.4.2 Preparación del Concreto Simple a) Dosificación f`c = 175 K/cm2 La dosificación del cemento, el agregado fino y el grueso se efectuarán en proporción al peso de estos elementos, y el agua se efectuó de acuerdo a su volumen. La dosificación para elaborar una mezcla de 1,0 metro cúbico de concreto de resistencia f’c = 175 K/cm2 fue de un porcentaje en peso de 1:2,2: 2,6 cemento : arena : piedra. Para efectos de medición en la fabricación de 1,00m3 de concreto en esta resistencia se utilizará 0,50m3 de arena gruesa, 0,80m3 de piedra zarandeada de 1”, 0,184m3 de agua, que mezclados con 7,80 bolsas de 42,50 Kilos de Cemento Tipo I, dará la proporción adecuada para fabricar concreto de 175K/cm2 de resistencia. b) Dosificación f’c = 175 K/cm + 30% de Piedra Grande (P.G.) Para la obtención de este tipo de mezcla se utilizó la misma dosificación para un concreto simple de f’c = 175 K/cm2. En el lugar de vaciado se alternará la utilización de la mezcla de concreto con la piedra de tamaño de 20cm. a 30cm. de diámetro o espesor. La especificación de utilizar como máximo un 30% de piedra grande como material adicional en reemplazo de mezcla de concreto en el lugar de vaciado, es lo que se denomina a la masa resultante como Concreto Ciclópeo. 1.9.3.5. OBRAS DE CONCRETO ARMADO 1.9.3.5.1 Dosificación f’c = 280 K/cm2 Esta dosificación fue utilizada para fabricar concreto reforzado con acero. Este tipo de concreto se utilizará en las Losas de operación de compuertas de la Bocatoma, muros de protección. Para la elaboración de concreto f’c = 280 K/cm2 se utilizará una proporción de 1:2:2.2 de materiales cemento:arena:piedra. Para la fabricación de 1,00m3 de concreto f’c = 280 Kg/cm2 se utilizó 0,50m3 de arena gruesa, 0,80m3 de piedra zarandeada de 1”, 0,184m3 de agua y 9 bolsas de Cemento tipo I. 1.9.3.6. ENCOFRADO Y DESENCOFRADO EL ENCOFRADO en esta obra se confeccionará de madera tornillo y triplay lupuna de 17mm. de espesor. Se confeccionaron paneles de la dimensión de cada plancha de triplay (4´x 8´), los cuales eran reforzados por barrotes de madera de 2” y 3” por todo el borde del panel y en su interior también.

Esta posición de reforzamiento permitirá una mayor duración de usos sin que se produzca deformaciones. El encofrado curvo se confeccionará mediante la construcción de moldes prefabricados de madera, utilizando para ello listones de tornillo de 1” x 4”, que unidos en forma vertical se pudo dar la curvatura requerida; una vez armado la estructura en curva, serán forrados con triplay de 4mm., para entregar un acabado curvo y liso. A este encofrado se le llama cerchas. Una vez confeccionados los paneles y cerchas, estos eran limpiados, lijados convenientemente y untados con aditivos desmoldantes, con este procedimiento se obtenía un concreto de acabado caravista. Posteriormente al uso de estos paneles, nuevamente eran limpiados convenientemente a fin de eliminar rastros de concreto seco, lechada, etc, y nuevamente untados con aditivo desmoldante para su nuevo uso. EL DESENCOFRADO será realizado en forma cuidadosa a fin de evitar daños en la superficie de las estructuras. La remoción del encofrado se realizaba una vez que el concreto adquiría la resistencia necesaria para soportar su propio peso. 1.9.3.7. CARPINTERÍA METÁLICA 1.9.3.7.1 Compuertas Deslizantes Las compuertas utilizadas en la Bocatoma serán de tipo ARMCO, con sus respectivos mecanismos de izaje. El trabajo de estas partidas consistirá en el suministro e instalación de estas compuertas deslizantes tipo tarjeta, cuyas dimensiones estarán indicadas en los planos de obra; así como también los mecanismos de izaje, braquetes, sellos, etc; es decir, todos los mecanismos necesarios para que trabaje eficientemente en las condiciones a que son sometidas en la actualidad.

1.10 Modalidad de ejecución La modalidad de ejecución será por contrata.

CAPITULO II: SITUACION ACTUAL

2. SITUACIÓN ACTUAL 2.1 Características 2.1.1 Clima La particularidad del distrito de Chaclacayo está en su clima seco y templado, siendo la contra estación del de Lima, es decir mientras en la capital peruana hace frio, Chaclacayo hace calor. Climatológicamente Chaclacayo varía entre las estaciones de otoño-invierno entre los 22°C y 13°C, siendo las mañanas de cielo cubierto con ligeras nieblas y a partir de las 11 horas brillo intenso de sol hasta el atardecer. Mientras que en las estaciones de primavera-verano la temperatura varía entre 13°C y 25°C, siendo la totalidad del día soleado, llegando incluso a temperaturas que superan los 28°C. La altitud del distrito varía de 522 msnm hasta los 1,667 msnm. 2.1.2 Precipitación De acuerdo a la estación de Chosica (periodo 1990 - 2017) la precipitación anual promedio es de 30mm. Las mayores precipitaciones se dan en los meses de enero a marzo, sin embargo se han registrado altas precipitaciones en los meses de abril como lo ocurrido el año 2012. Tabla N° 2: Variación de la precipitación mensual (mm)

2.1.3 Temperatura De acuerdo a la estación de Ñaña (operado por Senamhi), la temperatura varía entre 11 y 26 ºC. Las mayores temperaturas se dan en los meses de enero a marzo y las temperaturas más bajas en los meses de julio y agosto. Tabla N° 3: Variación de la temperatura mensual (°C) Temperatura

Ene

Feb

Mar

Abr

May

Jun

Jul

Ago

Set

Oct

Nov

Dic

Temp. Max.

25.6

26.6

26.1

25.7

24.2

21.4

29.7

20.0

21.2

22.7

23.2

24.3

Temp. Min.

16.8

17.7

17.5

16.6

15.0

12.5

10.8

9.5

11.1

14.1

15.1

16.3

Fuente: HIDROLOGIA: CAUDALES MAXIMOS DEL RÍO HUAYCOLORO

2.2 Vías de acceso y medios de transporte Para llegar a la zona del proyecto desde la ciudad de Lima es por la carretera central/Nicolás Ayllon, se sigue un tramo de 28 Km con dirección a Chosica. La carretera se encuentra en buen estado y es asfaltada en su totalidad. Tabla N° 4: Itinerario de acceso desde Lima a la zona del Proyecto

2.3 Ubicación de canteras de agregados y rellenos Se aprovecha el material del mismo río que abastecerá para la construcción del enrocado, espigon y bocatoma. Se dispone una cantidad suficiente de rocas y agrgados que cubre las necesidades del proyecto en toda su magnitud. Para otros agregados, grueso y fino se comprara puesto en obra.

2.4 Situación actual de la infraestructura existente La Comision de Usuarios La Estrella cuenta con dos bocatomas tipo rusticas que pertenecen a los canales derivadores Castrillejo y la Estrella. Estos canales derivarores tienen una longitud de 20.59 Km de los cuales 11.15 Km se encuentran revestidos y 9.44Km sin revestir. Tambien cuenta con 12 canales laterales de primer orden y uno de segundo orden. Ademas, cuenta con 15 alcantarillas, 4 aforadoes, 13 buzones y 3 aliviaderos. La infraestructura (bocatoma) tiene un grado de vulnerabilidad alta al estar emplazada en el mismo cauce del rio Rimac. Al ser de tipo rustica es frágil ante cualquier crecida del rio. Al ser la Comision de usuarios La Estrella integrante de la Junta de Usuarios Rimac los usuarios se encuentran organizados y tienen gran capacidad de respuesta ante cualquier eventualidad.

ESTRUCTURA DE CAPTACION: INVENTARIO DE BOCATOMAS Sector Hidráulico: Junta de Usuarios Rimac Sub Sector Hidraulico: Comisión de Usuarios La Estrella Operador de la Infraestructura Hidráulica: Comisión de Usuarios La Estrella

(1) 1 2

Cuadro Nº 01 Bocatomas Localización Canal de Observaciones Coordenadas Margen Tipo Estado Material Derivación Nombre Pregresiva Este Norte (2) (3) (4) Castrillejo 40+545 304211 8674708 I R R Otros Castrillejo Bocatoma rustica de piedras y caballetes La Estrella 39+520 303270 8674622 I R R Otros La Estrella Bocatoma rustica de piedras y caballetes

(1) (2) (3) (4) (5)

Número de Orden Tipo: Pe (Permanente), Sr (Semi-Rústico) y R (Rústico), según corresponda Estado: B (Bueno), R (Regular) y M Malo) Material: C (Concreto), M (Mampostería) y O (Otros) Operación: Manual o automático

Fuente de Agua N°

Rimac Rimac

CAPITULO III: INGENIERIA DEL PROYECTO

3. INGENIERIA DEL PROYECTO 3.1 Planteamiento Hidráulico: 3.1.1 Planificación física El planteamiento hidráulico consiste en la rehabilitación de la bocatoma Castrillejo con la finalidad de asegurar la captación de la dotación asignada a la Comisión de usuarios La Esterlla, por lo que se ha analizado el sistema para un caudal maximo para un periodo de retorno de 105 años. En base a la evaluación en campo y a las condiciones topográficas, se ha visto por conveniente que al expediente desarrollado, adicionar algunas estructuras necesarias para que hidráulicamente la bocatoma pueda funcionar y captar el caudal asignado (0.15 m3/s), sin problema alguno; estas estructuras son: 02 muros de proteccion, 01 canal de aproximación (50ml), 01 compuertas tipo izaje, 01 compuerta de limpia, 01 transicion de empalme con el canal existente. 3.1.2 Dimensionamiento y cálculos justificatorios Para dar inicio al diseño se calculó primero la sección del canal de conducción, para ello es necesario conocer el caudal, el cual fue otorgado por la Junta de Usuarios del sector hidráulico Rimac (JUSHR), para la Bocatoma La Estrella es de 0.15m3/s, la pendiente será de 1.3% y el material será de concreto simple y sección rectangular de espesor 0.15m. La rasante del canal se encuentra a la cota 588.84.

Con estos datos se procedio al calculo utilizando el software HCANALES.

Según los resultados tendrá una plantilla de 0.80m una altura total de 0.80m y tendrá una longitud de 2.0m.

La compuerta de limpia tendrá las mismas características y los datos para el calculo se muestran a continuación.

Según los resultados tendrá un ancho de 0.80m y una capacidad de descarga de 333.0 l/s. Para proteger el canal de conducción y la compuerta de limpia se ha previsto la construcción de dos muros de protección. Para diseñar los muros es necesario conocer la socavación en el lugar donde se emplazaran. Para ello se utilizo el software RIVER. Introduciendo el caudal de diseño para un periodo de retorno de 105 años se tiene:

Del plano topográfico se obtuvo la pendiente del rio en el tramo considerado y con las formulas de Petts, Simons y Henderson, Blench y Atunin, Maninng y Stickler, se obtuvo el ancho estable del cauce. Esto sirve para calcular el tirante en la zona considerada.

El ancho estable será de 87.0m, el tirante es de 0.90m con un bordo libre de 1.30m.

Para un Dm del cauce del rio de 15mm se puede calcular la socavación.

La profundidad de socavación es de 2.90m, el tirante de socavación es de 3.69 y la altura del muro 4.0m.

Para mayor seguridad la profundidad de cimentación del muro será de 3.50m, la altura del muro será de 4.0m. Ahora procedemos al análisis estructural del muro.

DISEÑO DE MURO DE CONCRETO ARMADO PARA LA CONTENCION DEL AGUA PROYECTO :

"REHABILITACION DE LA BOCATOMA CASTRILLEJO, DISTRITO CHACLACAYO, PROVINCIA Y REGION LIMA". PREDIMENSIONAMIENTO

DATOS Peso específico del relleno Peso específico del concreto Peso específico del agua Calidad diseño de concreto Ang.fricc.Intern. suelo a contener Capacidad portante del terreno Coef. de fricción concreto-terreno Espesor de recubrimiento del acero Esfuerzo de fluencia del acero

Sc=0 Kg/m2 t1=0.30 i2 = 0.15 i1 = 0.00

i1

i2

AGUA P a n t a l l a

1 h=4.00

1 H=4.45 hw=1.15

hr=0.40

RESULTADO DE ESTABILIDAD Soporte del suelo Exentricidad de la resultante Estabilidad al volteo Estabilidad al deslizamiento Fuerzas cortantes Base del muro OK En talón dorsal OK

gs g cº gw f'c Ø st f2 r fy

OK OK OK OK

1800.00 2400.00 1000.00 210.00 34.60 2.33 0.400 0.06 4200.00

Kg/m3 Kg/m3 Kg/m3 Kg/cm2 º Kg/cm2 m Kg/cm2

OK

En talón frontal OK Diente OK

hp= 0.20 h1=0.45 ho=0.15

t3

t4

t1

DIMENSIONAMIENTO DEL ACERO

Talon dorsal

Talon frontal A

t3=0.00 1.15 B1=1.00

t1

t4=0.60

B3=0.50 t2=0.90 B=2.80

B2=0.90

Acero vertical en muro Acero horizontal parte baja del muro Exterior Interior Acero horizontal parte alta del muro Exterior Interior Acero en talón dorsal Acero en talón frontal Acero en diente contra deslizam. Cortar la mitad del acero vertical a

Ø 5/8''

@ Smax 14.5 cm 23cm OK

1/2'' 1/2''

8.5 cm 45cm OK 17.0 cm 45cm OK

1/2'' 12.5 cm 1/2'' 25.5 cm 1/2'' 14.0 cm 5/8'' 22.0 cm 1/2'' 17.0 cm CALCULAR

45cm OK 45cm OK 45cm OK 45cm OK 45cm OK 2.84 m

La sección típica de los muros de protección aguas abajo y arriba se muestran a continuación.

Estos muros al ser de concreto armado llevan acero de refuerzo cuya disposición se muesta.

0.30 1/2'' @12.5cm

1/2'' @25.5cm

29.0cm 29.0cm

5/8'' @29cm 4.00 m 1/2'' @17cm

1/2'' @8.5cm

2.84 m 5/8'' @14.5cm 1/2'' @14cm

0.45 0.15

Forma alternada de colocar el acero vertical 5/8'' @22cm 1.00

0.90

1/2'' @17cm 1/2'' @17cm 0.90

Tambien, para mayor seguridad y darle una protección adicional a la captacion se a previsto un dentellon frontal de concreto f´c = 280 Kg/cm2 de 3.50m de profundidad y sobre el van colocados rieles para evitar la entrada de rocas a la captación. Tambien se ha previsto la conformación de un canal de aproximación con material propio del rio y la plantilla de este canal será recubierta con piedra grande de diámetro de 1.0m. Conociendo el tirante y las secciones de los canales se puede diseñar las compuertas.

Para la compuerta del canal de limpia se usaron los mismos criterios resultando.

Las compuertas van confinadas entre los muros de protección. Para la unión entre la estructura de captación y el canal existente se ha previsto una transición de 1.0m de largo como minimo.

Se ha previsto una loza de maniobras de concretro armado fc´=280 Kg/cm2, que va soportada por los muros de proteccion. El espesor de esta loza es de 0.20m y por seguridad lleva barandas de protección de fierro galvanizado de 2” de diámetro y altura de 0.90m.

3.2 Metas Fisicas Item 1 1.1 1.2 2 2.1

Descripción de la Meta Bocatoma Captacion Muros de proteccion Obras complementarias Mamposteria de piedra

Und

Cantidad

und und

1 3

u

2

3.3 Presupuesto de Obra

3.4 Cotizacion de los insumos mas incidentes

3.5 Planilla de metrados METRADOS "REHABILITACION DE LA BOCATOMA CASTRILLEJO, DISTRITO DE CHACLACAYO, PROVINCIA DE LIMA, FECHA PROPIET. MODALIDAD

:JULIO - 2018 :AUTORIDAD PARA LA RECONSTRUCCION CON CAMBIOS :CONTRATO

Item

Descripción

DEPART. PROV.

:LIMA :LIMA

Und.

Metrado

1.00 1.01 1.02 1.03 1.04 1.05

OBRAS PROVISIONALES CARTEL DE IDENTIFICACION DE LA OBRA DE 3 60 X 4 80 M. MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA PESADA CONSTRUCCION DE CAMPAMENTO DESVIO DE RIO TRAZO, NIVELACION DURANTE LA OBRA

und gb m2 m3 mes

1.00 1.00 35.00 480.00 3.00

2.00 2.01 2.02 2.03 2.04 2.05 2.06

MOVIMIENTO DE TIERRAS DESCOLMATACION DE CAUCE DE RIO EXCAVACION EN MATERIAL CONGLOMERADO A MANO RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO REFINE, NIVELACION Y COMPACTACION TERRENO NORMAL EXCAVACION PARA CONFORMACION CIMIENTO DE MUROS RELLENO COMPACTADO MANUAL MATERIAL PROPIO

m3 m3 m3 m2 m3 m3

1869.00 6.86 7.90 32.40 330.22 88.14

3.00 3.01 3.02 3.03

OBRAS DE CONCRETO SIMPLE ENCOFRADO Y DESENCOFRADO NORMAL CONCRETO SIMPLE f'c=175 kg/cm2 CONCRETO CICLOPEO f'c=175 KG/CM2+ 30% PG.

m2 m3 m3

256.82 4.38 145.89

4.00 4.01 4.02

OBRAS DE CONCRETO ARMADO CONCRETO f'c=280 kg/cm2 ACERO DE REFUERZO fy=4,200 kg/cm2

m3 Kg

148.70 8025.72

5.00 5.01 5.02 5.03

CARPINTERIA METALICA COMPUERTA METALICA DE 0.80x1.20m 1/4" C/ANGULO Ø 1/4"x3/4" und COMPUERTA METALICA DE 0.70x1.20m 1/4" C/ANGULO Ø 1/4"x3/4" und FABRICACION Y COLOCACION DE BARANDAS METALICAS (INC PINTURA) m

6.00 6.01 6.02

MITIGACION AMBIENTAL LIMPIEZA Y RESTAURACION DE PATIO DE MAQUINAS Y CASETAS SELLADO DE LETRINAS

m2 und

150.00 2.00

7.00 7.01

FLETE URBANO Y RURAL FLETE URBANO Y RURAL

GB

1.00

1.00 1.00 7.50

Analisis de costos unitarios Análisis de precios unitarios Presupuesto

0501009 REHABILITACION DE BOCATOMA

Subpresupuesto

Fecha presupuesto 001 "REHABILITACION BOCATOMA CASTRILLEJO Y LA ESTRELLA, DISTRITO DE CHACLACAYO, PROVINCIA DE LIMA, DEPARTAMENTO DE LIMA"

31/07/2018

Partida

01.01

Rendimiento

u/DIA

Código

Descripción Recurso

0147010002

OPERARIO

hh

1.0000

8.0000

20.96

167.68

0147010004

PEON

hh

1.0000

8.0000

15.29

122.32

CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m 1.0000

EQ. 1.0000 Unidad

Costo unitario directo por : u Cuadrilla

Cantidad

1,032.51

Precio S/.

Parcial S/.

Mano de Obra

290.00 Materiales 0202010005

CLAVOS PARA MADERA CON CABEZA DE 3"

kg

1.0000

3.04

3.04

0202010007

CLAVOS PARA MADERA CON CABEZA DE 4"

kg

0.5000

3.04

1.52

0202100010

PERNO HEXAGONAL DE 3/4" X 3 1/2"

pza

9.0000

0.92

8.28

0205010038

ARENA GRUESA (PUESTO EN OBRA)

m3

0.3600

50.90

18.32

0221000001

CEMENTO PORTLAND TIPO I (42.5 kg)

bls

0.9000

19.75

17.78

0230750110

GIGANTOGRAFIA

u

1.0000

150.00

150.00

0243040000

MADERA TORNILLO O SIMILAR

p2

70.0000

5.80

406.00

0244030024

TRIPLAY DE 8 mm

m2

8.6400

14.44

124.76

0254010001

PINTURA ESMALTE SINTETICO

gal

0.4320

29.66

12.81 742.51

Partida

01.02

Rendimiento

glb/DIA

Código

Descripción Recurso

0348040015

CAMION PLATAFORMA 6 X 4 300 HP 19 ton

MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPO 1.0000

EQ. 1.0000 Unidad

Costo unitario directo por : glb Cuadrilla

Cantidad

2.0000

16.0000

3,951.52

Precio S/.

Parcial S/.

Equipos hm

246.97

3,951.52 3,951.52

Partida

01.03

Rendimiento

m2/DIA

Código

Descripción Recurso

CONSTRUCCION DE CAMPAMENTO 50.0000

EQ. 50.0000 Unidad

Costo unitario directo por : m2 Cuadrilla

Cantidad

89.73

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1600

20.96

0147010004

PEON

hh

3.0000

0.4800

15.29

3.35 7.34 10.69

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.2000

2.90

0.58

0202010005

CLAVOS PARA MADERA CON CABEZA DE 3"

kg

0.1500

3.04

0.46

0205010004

ARENA GRUESA

m3

0.1500

50.90

0221000001

CEMENTO PORTLAND TIPO I (42.5 kg)

bls

0.3500

19.75

6.91

0243040000

MADERA TORNILLO O SIMILAR

p2

3.5000

5.80

20.30

0244030035

TRIPLAY DE 1.20x2.40x18 mm

u

0.3800

83.00

31.54

0266300003

CALAMINA TIPO SABANA ROJA 1.10 X 3.05 m

pza

0.2770

40.00

11.08

% MO

5.0000

10.69

7.64

78.51 Equipos 0337010001

HERRAMIENTAS MANUALES

0.53 0.53

Partida

01.04

Rendimiento

m3/DIA

Código

Descripción Recurso

DESVÍO DE RIO 800.0000

EQ. 800.0000 Unidad

Costo unitario directo por : m3 Cuadrilla

Cantidad

4.73

Precio S/.

Parcial S/.

Mano de Obra 0147010004

PEON

hh

1.0000

0.0100

15.29

0.15 0.15

Equipos 0349040035

TRACTOR DE ORUGAS DE 270-295 HP

hm

0398010137

HERRAMIENTA MANUAL

% PU

Partida

01.05

Rendimiento

mes/DIA

Código

Descripción Recurso

1.0000

0.0100

434.60

4.35

5.0000

4.50

0.23 4.58

TRAZO Y NIVELACION DURANTE LA OBRA 60.0000

EQ. 60.0000 Unidad

Costo unitario directo por : mes Cuadrilla

Cantidad

1,238.52

Precio S/.

Parcial S/.

Mano de Obra 0147000032

TOPOGRAFO

hh

96.0000

12.8000

20.96

268.29

0147010003

OFICIAL

hh

96.0000

12.8000

16.99

217.47 485.76

Materiales 0229060005

YESO DE 28 Kg

bls

1.5000

15.00

22.50

0243040000

MADERA TORNILLO O SIMILAR

p2

30.0000

5.80

174.00

0254170001

PINTURA ESMALTE

gal

0.1000

29.66

2.97 199.47

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

0337010102

MIRA Y JALONES

hm

0337020037

WINCHA DE 30 m

u

0349190003

NIVEL TOPOGRAFICO CON TRIPODE

he

5.0000

485.76

24.29

96.0000

12.8000

10.00

128.00

0.2000

85.00

17.00

96.0000

12.8000

30.00

384.00 553.29

Partida

02.01

DESCOLMATACION DE CAUCE DE RIO

Rendimiento

m3/DIA

Código

Descripción Recurso

1,000.0000

EQ. 1,000.0000 Unidad

Costo unitario directo por : m3

3.69

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147000037

OPERARIO

hh

0.5000

0.0040

20.96

0.08

0147010004

PEON

hh

1.0000

0.0080

15.29

0.12 0.20

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

0349040035

TRACTOR DE ORUGAS DE 270-295 HP

hm

1.0000

5.0000

0.20

0.01

0.0080

434.60

3.48 3.49

Partida

02.02

EXCAVACION EN MATERIAL CONGLOMERADOA MANO

Rendimiento

m3/DIA

Código

Descripción Recurso

2.5000

EQ. 2.5000 Unidad

Costo unitario directo por : m3

62.79

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010003

OFICIAL

hh

0.2000

0.6400

16.99

10.87

0147010004

PEON

hh

1.0000

3.2000

15.29

48.93 59.80

Equipos 0337010001

HERRAMIENTAS MANUALES

Partida

02.03

Rendimiento

m3/DIA

Código

Descripción Recurso

% MO

5.0000

59.80

2.99 2.99

RELLENO COMPACTADO MANUAL- CON MATERIAL DE PRESTAMO 15.0000

EQ. 15.0000 Unidad

Costo unitario directo por : m3

66.28

Cuadrilla

Cantidad

Precio S/.

Parcial S/. 4.53

Mano de Obra 0147010003

OFICIAL

hh

0.5000

0.2667

16.99

0147010004

PEON

hh

1.0000

0.5333

15.29

8.15 12.68

Materiales 0205010019

MATERIAL DE PRESTAMO SELECCIONADO OBRA

m3

1.1000

35.00

38.50 38.50

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

0349030001

COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP

hm

1.0000

5.0000

12.68

0.63

0.5333

27.13

14.47 15.10

Partida

02.04

REFINE Y NIVELACION EN TERRENO NORMAL

Rendimiento

m2/DIA

Código

Descripción Recurso

35.0000

EQ. 35.0000 Unidad

Costo unitario directo por : m2

3.68

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

1.0000

0.2286

15.29

3.50

Mano de Obra 0147010004

PEON

hh

3.50 Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

5.0000

3.50

0.18 0.18

Partida

02.05

EXCAVACION PARA CONFORMACION DE CIMIENTO DE MUROS

Rendimiento

m3/DIA

Código

Descripción Recurso

640.0000

EQ. 640.0000 Unidad

Costo unitario directo por : m3

4.49

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147000037

OPERARIO

hh

0.2000

0.0025

20.96

0.05

0147010004

PEON

hh

2.0000

0.0250

15.29

0.38 0.43

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

0349040094

EXCAVADORA SOBRE ORUGAS 170-250 HP

hm

1.0000

5.0000

0.43

0.02

0.0125

322.83

4.04 4.06

Partida

02.06

RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO_1

Rendimiento

m3/DIA

Código

Descripción Recurso

6.0000

EQ. 6.0000 Unidad

Costo unitario directo por : m3 Cuadrilla

Cantidad

68.84

Precio S/.

Parcial S/.

Mano de Obra 0147010003

OFICIAL

hh

0.5000

0.6667

16.99

11.33

0147010004

PEON

hh

1.0000

1.3333

15.29

20.39 31.72

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

0349030001

COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP

hm

1.0000

3.0000

31.72

0.95

1.3333

27.13

36.17 37.12

Partida

03.01

ENCOFRADO Y DESENCOFRADO NORMAL

Rendimiento

m2/DIA

Código

Descripción Recurso

14.0000

EQ. 14.0000 Unidad

Costo unitario directo por : m2

50.71

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.5714

20.96

11.98

0147010003

OFICIAL

hh

1.0000

0.5714

16.99

9.71

0147010004

PEON

hh

1.0000

0.5714

15.29

8.74 30.43

Materiales 0202000008

ALAMBRE NEGRO RECOCIDO # 8

kg

0.1750

2.90

0202010003

CLAVOS PARA MADERA CON CABEZA DE 2"

kg

0.2000

3.04

0.51 0.61

0243040000

MADERA TORNILLO O SIMILAR

p2

1.8000

5.80

10.44

0244030035

TRIPLAY DE 1.20x2.40x18 mm

u

0.0868

83.00

7.20 18.76

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

5.0000

30.43

1.52 1.52

Partida

03.02

CONCRETO f'c=175 kg/cm2

Rendimiento

m3/DIA

Código

Descripción Recurso

15.0000

EQ. 15.0000 Unidad

Costo unitario directo por : m3

379.49

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

2.0000

1.0667

20.96

22.36

0147010003

OFICIAL

hh

2.0000

1.0667

16.99

18.12

0147010004

PEON

hh

12.0000

6.4000

15.29

97.86 138.34

Materiales 0205000006

PIEDRA CHANCADA DE 1 1/2"

m3

0.6100

62.90

0205010004

ARENA GRUESA

m3

0.4900

50.90

38.37 24.94

0221000001

CEMENTO PORTLAND TIPO I (42.5 kg)

bls

8.4300

19.75

166.49 229.80

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

3.0000

138.34

4.15

0348010086

MEZCLADORA DE CONCRETO DE 11-12p3 18 HP

hm

1.0000

0.5333

10.71

5.71

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

0.5000

0.2667

5.60

1.49 11.35

Partida

03.03

CONCRETO CICLOPEO f'c=175 kg/cm2 + 30 % PG.

Rendimiento

m3/DIA

Código

Descripción Recurso

24.0000

EQ. 24.0000 Unidad

Costo unitario directo por : m3

352.54

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

2.0000

0.6667

20.96

13.97

0147010003

OFICIAL

hh

2.0000

0.6667

16.99

11.33

0147010004

PEON

hh

8.0000

2.6667

15.29

40.77 66.07

Materiales 0205000033

PIEDRA GRANDE

m3

0.5040

35.00

17.64 17.64

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

0349070004

VIBRADOR DE CONCRETO 4 HP 2.40"

hm

1.0000

2.0000

66.07

1.32

0.3333

5.60

1.87 3.19

Subpartidas 900510010610

CONCRETO f'c=175 kg/cm2

m3

0.7000

379.49

265.64 265.64

Partida

04.01

CONCRETO f 'c=280 kg/cm2

Rendimiento

m3/DIA

Código

Descripción Recurso

4.5000

EQ. 4.5000 Unidad

Costo unitario directo por : m3

430.98

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

1.7778

20.96

37.26

0147010003

OFICIAL

hh

1.0000

1.7778

16.99

30.20

0147010004

PEON

hh

3.0000

5.3333

15.29

81.55 149.01

Materiales 0205000003

PIEDRA CHANCADA DE 1/2"

m3

0.6100

62.90

0205010004

ARENA GRUESA

m3

0.4100

50.90

20.87

0221000001

CEMENTO PORTLAND TIPO I (42.5 kg)

bls

10.9000

19.75

215.28

38.37

274.52 Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

5.0000

149.01

7.45 7.45

Partida

04.02

Rendimiento

kg/DIA

Código

Descripción Recurso

ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 240.0000

EQ. 240.0000 Unidad

Costo unitario directo por : kg

4.84

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.0333

20.96

0.70

0147010003

OFICIAL

hh

1.0000

0.0333

16.99

0.57

0147010004

PEON

hh

0.5000

0.0167

15.29

0.26 1.53

Materiales 0202000007

ALAMBRE NEGRO RECOCIDO # 16

kg

0.0500

2.90

0.15

0203020003

ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60

kg

1.0500

2.74

2.88 3.03

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

0348960009

CIZALLA ELECTRICA PARA DE FIERRO

hm

0.5000

5.0000

1.53

0.08

0.0167

12.00

0.20 0.28

Partida

05.01

Rendimiento

u/DIA

Código

Descripción Recurso

COMPUERTA METÁLICA TIPO IZAJE 1/4" x 1.20 x 0.80m 1.0000

EQ. 1.0000 Unidad

Costo unitario directo por : u

3,123.70

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

8.0000

20.96

167.68

0147010004

PEON

hh

1.0000

8.0000

15.29

122.32 290.00

Materiales 0209030072

COMPUERTA METALICA TIPO IZAJE DE 1/4" x 1.20 x 0.80m u

0337010001

HERRAMIENTAS MANUALES

1.0000

2,825.00

3.0000

290.00

2,825.00 2,825.00

Equipos % MO

8.70 8.70

Partida

05.02

Rendimiento

u/DIA

Código

Descripción Recurso

COMPUERTA METÁLICA TIPO IZAJE 1/4" x 1.20 x 0.70m 1.0000

EQ. 1.0000 Unidad

Costo unitario directo por : u

2,863.70

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

8.0000

20.96

167.68

0147010004

PEON

hh

1.0000

8.0000

15.29

122.32 290.00

Materiales 0209030073

COMPUERTA METALICA TIPO IZAJE DE 1/4" x 1.20 x 0.70m u

1.0000

2,565.00

2,565.00 2,565.00

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

3.0000

290.00

8.70 8.70

Partida

05.03

Rendimiento

m/DIA

Código

Descripción Recurso

FABRICACION Y COLOCACION DE BARANDAS METALICAS (INCLUYE PINTURA) 10.0000

EQ. 10.0000 Unidad

Costo unitario directo por : m

468.29

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147000037

OPERARIO

hh

1.0000

0.8000

20.96

16.77

0147010004

PEON

hh

4.0000

3.2000

15.29

48.93 65.70

Materiales 0202080031

PERNO DE ANCLAJE 5/8" X 0.50 m

pza

3.2000

8.58

27.46

0229510001

OXIGENO

m3

0.6000

7.10

4.26

0229510003

ACETILENO

m3

0.2000

27.01

5.40

0229550097

SOLDADURA AWS E7018 O SIMILAR

kg

3.5000

15.12

52.92

0251040129

PLATINA DE ACERO 3/8" X 0.125 X 2.20 m

m2

0.2300

69.19

15.91

0251040130

PLATINA DE ACERO 3/8" (B3)

m2

0.0900

41.07

3.70

0256020083

PLANCHA DE ACERO 5/8" x 0.20 x 0.17 m.

pza

0.8000

26.44

21.15

0265170100

TUBO DE FIERRO 2" SCH-40

m

1.0500

46.86

49.20

0265170101

TUBO DE FIERRO 1" SCH-40

m

2.1000

23.60

49.56 229.56

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

3.0000

65.70

1.97

0348070022

SOLDADORA ELECTRICA TRIFASICA 400 A

hm

0.5000

0.4000

13.20

5.28

0348210066

EQUIPO DE OXICORTE

hm

0.5000

0.4000

8.68

3.47 10.72

Subpartidas 900401160311

PINTADO DE BARANDAS

tot

1.0500

154.58

162.31 162.31

Partida

06.01

Rendimiento

m2/DIA

Código

Descripción Recurso

LIMPIEZA Y RESTAURACION DE PATIO DE MAQUINAS Y CASETAS 80.0000

EQ. 80.0000 Unidad

Costo unitario directo por : m2

5.42

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

Mano de Obra 0147010002

OPERARIO

hh

1.0000

0.1000

20.96

2.10

0147010004

PEON

hh

2.0000

0.2000

15.29

3.06 5.16

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

5.0000

5.16

0.26 0.26

Partida

06.02

Rendimiento

u/DIA

Código

Descripción Recurso

SELLADO DE LETRINAS 1.0000

EQ. 1.0000 Unidad

Costo unitario directo por : u

1,439.92

Cuadrilla

Cantidad

Precio S/.

Parcial S/.

2.0000

16.0000

15.29

244.64

Mano de Obra 0147010004

PEON

hh

244.64 Materiales 0205030071

PIEDRA ZARANDEADA DE 1/2"

m3

4.5000

62.90

0229030103

CAL VIVA

kg

60.0000

15.00

283.05 900.00 1,183.05

Equipos 0337010001

HERRAMIENTAS MANUALES

% MO

5.0000

244.64

12.23 12.23

Partida

07.01

Rendimiento

glb/DIA

Código

Descripción Recurso

FLETE URBANO Y RURAL 60.0000

EQ. 60.0000 Unidad

Costo unitario directo por : glb Cuadrilla

11,020.60

Cantidad

Precio S/.

Parcial S/.

1.0000

11,020.60

11,020.60

Materiales 0232000032

FLETE TERRESTRE

glb

11,020.60

3.6 Relacion de materiales e insimos

3.7 Calculo de flete urbano y rural CALCULO DEL FLETE TERRESTRE PROYECTO:

REHABILITACION BOCATOMA CASTRILLEJO, DISTRITO DE CHACLACAYO, PROVINCIA DE LIMA, DEPARTAMENTE O DE LIMA JULIO 2018

FECHA: ACCESO A LA OBRA

DISTANCIA APROX (KM)

TERRESTRE RURAL

43.2 0

PESO TOTAL DE LOS MATERIALES

176,030.04 kg

FLETE TERRESTRE (Materiales) UNIDAD DE TRANSPORTE: CAPACIDAD DE LA UNIDAD DE TRANSPORTE COSTO DE TRANSPORTE POR VIAJE: N° DE VIAJES

FLETE TERRESTRE

TERRESTRE CAMION 12,000 Kg 750.00 S/./Viaje 10.00 Viaje S/.7,500.00

SERVICIO DE CARGA Y DESCARGA DE MATERIALES UNIDAD DE TRANSPORTE: PESO TOTAL CAPACIDAD DE CARGA COSTO DE TRANSPORTE: N° DE VIAJES

FLETE RURAL:

PEON 176,030.04 50.00 1.00 3,520.60 S/.3,520.60

KG KG/VIAJE SOLES/VIAJE

RESUMEN FLETE TERRESTRE: FLETE RURAL: SERVICIO DE CARGA Y DESCARGA DE MATERIALES

TOTAL

3.8 Formula Polinomica

S/.7,500.00 S/.0.00 S/.3,520.60 S/.11,020.60

3.9 Desagregado de gastos generales DESAGREGADO DE GASTOS GENERALES "REHABILITACION DE LA BOCATOMA CASTRILLEJO, DISTRITO DE CHACLACAYO, PROVINCIA DE LIMA, DEPARTAMENTO DE LIMA" FECHA

:JULIO - 2018

DEPART.

:LIMA

PROPIET.

:AUTORIDAD PARA LA RECONSTRUCCION CON CAMBIOS

PROV.

:LIMA

MODALIDAD

:CONTRATO

DISTRITO

:CHACLACAYO

LUGAR

:SECTOR 2

PLAZO DE EJECUCIÓN : 90 DIAS CALENDARIOS Categoria Mod. de Gasto Aplic. GASTOS DE CAPITAL INVERSIONES:

ESPECIFICACION DEL GASTO

UND

CANT

PRESUPUESTO P.UNITARIO

PARCIAL

2,940.00

GASTOS GENERALES

2.6.2.2.2.2 2.6.2.2.2.2

GASTOS ADMINISTRATIVOS - TECNICOS. LIQUIDACION TECNICA - FINANCIERA.

GLB GLB

1.00 1.00

140.00 2,800.00

140.00 2,800.00

17,315.79

GASTOS GENERALES RELACIONADOS CON EL TIEMPO DE EJECUCION DE OBRA

2.6.2.2.2.2 2.6.2.2.2.2 2.6.2.2.2.2 2.6.2.2.2.2

RESIDENTE DE OBRA UTILES DE ESCRITORIO BOTIQUIN PLACA RECORDATORIA

TOTAL

Mes Mes Mes GLB

3.00 1.00 1.00 1.00

5,500.00 215.79 250.00 350.00

16,500.00 215.79 250.00 350.00

COSTO TOTAL GASTOS GENERALES

3.10 Especificaciones técnicas 01. OBRAS PROVICIONALES 01.01. CARTEL DE OBRA DE OBRA 3.60m x 4.80m Previo al inicio de las Obras se deberá colocar el Cartel de Obra con forma Rectangular y de las siguientes dimensiones: 4.80 m de ancho y 3.60 m de alto, contendrá: el nombre de la Entidad Pública, nombre del Proyecto, Monto de la Inversión, la fuente de Financiamiento, el Plazo de Duración, el nombre del Contratista y la Modalidad de Contratación. La ubicación será designada por el supervisor en coordinación con la Entidad. El diseño será impreso en una gigantografía sobre lamina plastificada (Banner) impreso de 13 onzas con dimensiones: 4.80 x 3.60m, con calidad de impresión mínima full color de 800 DPI (puntos por pulgada). Los traslapes en la impresión del banner deberán tener un mínimo de tres centímetros (3 cm). La estructura deberá ser con madera mohena o tornillo, seco y de buena calidad. Clavos calamineros 2 ½”x9. Se construirá un bastidor (marco) de madera tornillo, conformado por listones de 4”x2” con tres (3) parantes verticales de 4”x4 empotrados al piso. Cada banner será fijado al bastidor con clavos calamineros, espaciados como máximo a 70 cm uno del otro y en las esquinas. MÉTODO DE MEDICIÓN El trabajo ejecutado para esta partida se medirá por Unidad (Unid), de cartel de obra. BASE DE PAGO La presente partida estará pagada por unidad (Unid) de cartel de obra.

20,255.79

01.02. MOVILIZACION Y DESMOVILIZACION DE MAQ. PESADA. Comprende el suministro y disponibilidad de los equipos y maquinaria necesaria para la ejecución de los trabajos y que requieren su transporte hasta el lugar de la obra, y su salida una vez concluidos los trabajos, de acuerdo a la relación de equipo y maquinaria presentada en el presupuesto de obra y/o a los cambios aprobados por el Supervisor. El Contratista presentará una relación del equipo a emplear en la obra con el cronograma de utilización correspondiente, el cual formará parte de la Oferta Técnica. Este cronograma se usará para programar los gastos de transporte de los equipos y maquinarias requeridos. La maquinaria deberá estar en perfectas condiciones operativas, lo que será verificado por el Supervisor. MÉTODO DE MEDICIÓN Y DE PAGO Esta partida se medirá y valorizará con la unidad de medida (GLB) de acuerdo al presupuesto. MÉTODO DE MEDICIÓN El trabajo ejecutado se medirá en forma Global (Glb), debiendo ser aprobado por el Ingeniero Supervisor. Descripción: Esta partida, considera todo el trabajo para acondicionar en el lugar de la obra; los ambientes provisionales destinados a la administración, almacén, depósito, vestidores, servicios higiénicos y guardianía para el personal obrero y técnico durante la ejecución de la obra, elaborados con material liviano prefabricado, con sus respectivas instalaciones. Control: La supervisión deberá aprobar la ubicación, disposición de ambientes, materiales y acabados; así como exigir su cumplimiento, pudiendo rechazar los que no sean satisfactorios. Método de Construcción: Este ítem está referido al acondicionamiento de ambientes provisionales necesarios para el personal técnico y obrero, serán de materiales prefabricados, como triplay con listonería de madera, techo liviano acanalado u otros sistemas similares; todo debidamente acondicionado y con las instalaciones mínimas necesarias. Además de los puntos de iluminación, deberán tener puertas con chapas de seguridad. Método de medición: La unidad de medición corresponde a la cantidad de metros cuadrados (m2) que abarcan dichas estructuras provisionales durante el transcurso de la obra. Condiciones de Pago:

El cálculo estimado será pagado al precio unitario del contrato y de acuerdo al método de medición, constituyendo dicho precio unitario, compensación plena por mano de obra, leyes sociales, equipos, herramientas y todos los imprevistos necesarios para completar la partida

01.03. DESVÍO DE RIO El Ingeniero Residente implementará una brigada para realizar los trabajos de desviación del rio, Para desviar el rio se realizara con yutes de arena o costales que serán llenos de arena u otro material de no permita filtrar al agua hacia la obra Durante la obra antes de hacer la excavación este desvío se hará para que sea el trabajo con mayor eficiencia y también para realizar las excavaciones tanto para el colchón anti socavante y para los muros de contención Todas las obras serán construidas de acuerdo con los trazos, gradientes y dimensiones mostradas en los planos, complementadas o modificadas por el Ingeniero Supervisor. La responsabilidad completa por el mantenimiento o alineamiento y gradientes, recae sobre el Ingeniero Residente. En caso de encontrar divergencias entre las condiciones reales del terreno y los datos de los planos, el Ingeniero Residente adecuará el desvío del rio a las condiciones actuales del caudal, de conformidad con el Ingeniero Supervisor. UNIDAD DE MEDIDA Metros cúbicos (M3) METODO DE MEDICION Esta partida será cuantificada de acuerdo al metrado avanzado BASES DE PAGO: El pago será de acuerdo al metrado avanzando para esta partida

01.04. TRAZO Y NIVELACION DURANTE LA OBRA Comprende el suministro de mano de obra, materiales, equipo para los trabajos topográficos a nivel constructivo de las obras (nivelación de puntos perimetrales, ejes constructivos, control de rasante, ubicación y control de los BMs, etc.), incidiéndose en los puntos perimetrales y los ejes constructivos. MODO DE EJECUCIÓN Deberán establecerse marcas y señales fijas de referencia en campo. Durante la verificación de la cota de rasante se colocaran plantillas donde se requiera, tratando de evitar en todos los casos secciones con rasante en relleno.

Se podrá modificar en todo o en parte, cuando sea necesario, los diseños que se incluyan dentro de los documentos del proyecto. Mas éstos se harán con autorización expresa de la Supervisión. UNIDAD DE MEDIDA Los trabajos se miden por mes. FORMA DE PAGO El pago se realizará de acuerdo al costo unitario definido en el Proyecto, comprendiendo dicho pago la compensación total para completar satisfactoriamente el trabajo.

02. MOVIMIENTO DE TIERRAS Las especificaciones contenidas en este capítulo, serán aplicadas al movimiento de tierras en superficie, de acuerdo a lo previsto en los planos de doseño, para construcción de las obras, incluyendo los trabajos de excavaciones, rellenos transporte de grava y/roca Los trabajos que comprende éste ítem abarcan el suministro. operación y mantenimiento de todos los equipos y herramientas, así como también el empleo de la mano de obra, materiales y combustibles que fueran necesarios para realizar los trabajos. Las excavaciones serán efectuadas según los ejes, rasantes y niveles indicados en los planos de diseño, y se llevarán a cabo aplicando medios apropiados elegidos por el INGENIERO RESIDENTE. Los cambios de los niveles o líneas de excavación indicados en los planos, se realizarán previa autorización de la SUPERVISIÓN y serán efectuados por el INGENIERO RESIDENTE. Pudiendo realizarse variaciones de trazo y niveles, de acuerdo con las condiciones que se presenten durante la excavación proyectada, previa autorización de la SUPERVISIÓN. El INGENIERO RESIDENTE deberá proceder a las excavaciones, después que haya procedido al levantamiento de las secciones transversales del terreno natural aprobado por la SUPERVISIÓN. Se incluye en éste ítem, la protección de las excavaciones de todos los cortes y refines de sus taludes. así como la preparación del fondo de las excavaciones para la cimentación de las rocas que posteriormente se emplazarán en estos lugares. En las partidas de excavaciones y rellenos, el precio unitario no incluirá el costo de los trabajos de carguío del material a transportar. La excavación excesiva o sobre excavación efectuada por el INGENIERO RESIDENTE será por su cuenta, a excepción de la ordenada por la SUPERVISIÓN y la sobre excavación será rellenada de acuerdo a las instrucciones de la SUPERVISIÓN, con materiales suministrados y colocados por cuenta del INGENIERO RESIDENTE.

Respecto al manejo y ubicación de botaderos, para minimizar los impactos ambientales relacionados con la inadecuada disposición de los materiales sobrantes, se recomienda se ubiquen en zonas de canteras abandonadas o suelos estériles sin ningún tipo de cobertura vegetal, pudiendo rellenarse con material propio áreas inundadas, evitando la proliferación de mosquitos y otros agentes. En todo caso se deberá evitar utilizar zonas inestables o áreas de importancia ambiental como áreas agrícolas.

02.01. DESCOLMATACION CAUCE DE RIO En general, para medición, la Descolmatación en el cauce del rio serán clasificadas como material suelto. Descolmatación en Material conglomerado: La excavación en material conglomerado suelto consiste en la remoción y levantamiento de todos los materiales que pueden ser removidos con maquinaria pesada tipo tractor de orugas ó similar de 270 - 295 H.P. El INGENIERO RESIDENTE deberá proceder a las excavaciones en material suelto. después que haya procedido a la limpieza y al levantamiento topográfico de secciones transversales del terreno natural aprobado por la SUPERVISIÓN. ALCANCE DE LOS TRABAJOS El servicio contempla el suministro de la mano de obra, materiales. equipo y la ejecución de todas las operaciones necesarias para conformar los rellenos semicompactados de los taludes del río con material propio. El costo incluye el riego de la capa anterior. la extracción del materia del sitio, extendido. Homogenización y semi-compactación. Esta actividad se llevará a cabo con un tractor que empujará y acopiará el material; este material será cargado y transportado con la misma máquina tractor de orugas ó similar de 270 - 295 H.P. Las capas semi-compactadas serán controladas con niveles topográficos y permanentemente El perfilado de los taludes y la inclinación de los taludes será verificado topográficamente. MATERIALES Los materiales utilizados para la construcción de los rellenos semi-compactados con material propio deberán ser obtenidos de excavaciones. material de lecho de río del sitio ubicado paralelamente a la franja de la obra y/o de los bancos de escombros, previamente aprobados por la SUPERVISIÓN. Habiéndose previsto

primero la eliminación del material con materia orgánica para su posterior empuje con tractor de orugas ó similar de 270 - 295 H.P para formar el talud del río. COLOCACIÓN Antes de colocar los rellenos semi-compactados. la superficie de fundación deberá estar debidamente regularizada. limpia, tratada y semi-compactada uniformemente con el paso de la excavadora según especificaciones u ordenado por la SUPERVISIÓN, quien lo aprobará. Los rellenos se colocarán en capa horizontales de 0.40 m de espesor y/o según las indicaciones de la SUPERVISIÓN. Antes de la colocación de la capa sucesiva, la superficie de la capa anterior será humedecida. CONTENIDO DE AGUA La uniformidad de contenido de agua en las diversas zonas del relleno, será controlada por su coeficiente de variación, que tendrá que ser inferior al 20% correspondiente a cada tramo, con el fin de lograr la semi-compactación especificada y/o indicada por la SUPERVISIÓN. SEMI-COMPACTACIÓN Cualquier capa tendrá que ser semi-compactada antes de la colocación de la capa sucesiva. El área de compactación durante la construcción tendrá que ser mantenida a un nivel uniforme. El material tendrá que ser extraído y semicompactado en estratos de la mayor extensión posible. FORMA DE PAGO La unidad de medida para el pago es el metro cubico (m3), de relleno semicompactado con material propio ejecutado y perfilado de talud, de acuerdo a los planos y especificaciones técnicas.

02.02. EXCAVACION EN MATERIAL CONGLOMERADO Dentro de esta clasificación están considerados los terrenos en tierra suelta, cantos rodados, grabas, arena, limos, arcillas, cenizas volcánicas, tierras de cultivo, material calcáreo disgregado y todo otro material o combinación de materiales no incluido en la clasificación de excavación en rocas. También se incluye peinado de taludes y la definición de las secciones de las cunetas. Esta partida comprende el conjunto de actividades para la excavación, corte, eliminación y transporte hasta él límite de acarreo libre de materiales sueltos con uso de equipos pesados y de acuerdo a las dimensiones, pendientes y cotas indicadas en los planos del proyecto.

EQUIPO El equipo empleado deberá ser compatible con los procedimientos de ejecución adoptados y requiere la aprobación previa del Supervisor, teniendo en cuenta que su capacidad y eficiencia se ajuste al programa de ejecución de los trabajos y al cumplimiento de las exigencias de la especificación. Se hará uso de excavadora sobre orugas 170-250 HP. MEDICIÓN El trabajo efectuado se medirá en metros cúbicos (m3), medido en su posición original. FORMA DE PAGO El pago se efectuará al precio unitario establecido en el contrato, por metro cúbico (m3). Dicho precio y pago constituirán compensación total por el equipo, mano de obra, herramientas e imprevistos necesarios para la excavación realizada.

02.03. RELLENO Y COMPACTADO CON MATERIAL DE PRÉSTAMO Alcance del Trabajo Comprende el suministro y disponibilidad del equipo, herramientas, materiales y mano de obra necesaria para efectuar el relleno compactado con material de préstamo en capas de espesor compactadas no mayor de quince (15) cm, de manera de rellenar los espacios existentes entre las estructuras terminadas y el terreno natural, hasta alcanzar las cotas exigidas, de acuerdo a lo indicado en los planos y aprobado por el Ingeniero Supervisor. Ejecución Los trabajos de relleno se realizará en capas sensiblemente horizontales no mayores de quince (15) cm de espesor compactado, según se indique en los planos o lo recomendado por el Ingeniero Supervisor. El material de relleno será aprobado por el supervisor. La compactación se efectuará una vez que el material contenga la humedad adecuada empleando medios mecánicos. Se tendrá especial cuidado en evitar presiones desiguales alrededor de las estructuras así como producir daños en los mismos. Medición y Pago Se medirá por metro cúbico (m3). Se determinará los volúmenes de relleno compactado en las estructuras de acuerdo a las secciones mostradas en los planos y aprobadas por el Ingeniero Supervisor. El pago se efectuará mensualmente y deberá ser aprobado por el Ingeniero Supervisor de acuerdo al precio unitario en la partida.

02.04. REFINE, NORMAL

NIVELACIÓN Y COMPACTACIÓN EN TERRENO

Después de producida la excavación, el contratista deberá refinar el fondo de la excavación y nivelarla de acuerdo a los requerimientos establecidos en los planos, de forma tal que el fondo de la zanja, presente una superficie plana y nivelada. El refine consiste en el perfilamiento tanto de las paredes como del fondo, teniendo especial cuidado. La nivelación se efectuara en el fondo de la zanja, con el tipo de cama de apoyo aprobada por la Supervisión, utilizando como cama de apoyo el mismo material de la zanja ya que se encuentra conformada por arena. MEDICIÓN Y FORMA DE PAGO La unidad de medida es el metro cuadrado (M2). La forma de pago se efectuará de acuerdo al avance calculado en metro cuadrado (M2).

02.05. EXCAVACION PARA CONFORMACION DE CIMENTACION DE MUROS Excavaciones masivas Estas excavaciones se realizaron para conformar las secciones de la uña, así como para cimentar o alojar las estructuras de acuerdo con los alineamientos, perfiles y secciones señalados en los planos, esto se realizará con la finalidad de lograr limpieza y un adecuado trabajo topográfico, logrando descolmatar el terreno hasta la cota indicada en los planos. El material resultante de la excavación fue colocado a los extremos del área de trabajo para poder ser posteriormente esparcido o poder ser empleado para completar el relleno de huecos que puedan estorbar el normal desarrollo de la obra. UNIDAD DE MEDIDA Metros cúbicos (M3) METODO DE MEDICION Esta partida será cuantificada de acuerdo al metrado avanzado BASES DE PAGO: El pago será de acuerdo al metrado avanzando para esta partida.

02.06. RELLENO Y COMPACTACION CON MATERIAL PROPIO Alcance del Trabajo Comprende el suministro y disponibilidad del equipo, herramientas, materiales y mano de obra necesaria para efectuar el relleno compactado

con material de propio en capas de espesor compactadas no mayor de quince (15) cm, de manera de rellenar los espacios existentes entre las estructuras terminadas y el terreno natural, hasta alcanzar las cotas exigidas, de acuerdo a lo indicado en los planos y aprobado por el Ingeniero Supervisor. Ejecución Los trabajos de relleno se realizará en capas sensiblemente horizontales no mayores de quince (15) cm de espesor compactado, según se indique en los planos o lo recomendado por el Ingeniero Supervisor. El material de relleno será aprobado por el supervisor. La compactación se efectuará una vez que el material contenga la humedad adecuada empleando medios mecánicos. Se tendrá especial cuidado en evitar presiones desiguales alrededor de las estructuras así como producir daños en los mismos. Medición y Pago Se medirá por metro cúbico (m3). Se determinará los volúmenes de relleno compactado en las estructuras de acuerdo a las secciones mostradas en los planos y aprobadas por el Ingeniero Supervisor. El pago se efectuará mensualmente y deberá ser aprobado por el Ingeniero Supervisor de acuerdo al precio unitario en la partida. 03. CONCRETO SIMPLE 03.01. ENCOFRADO Y DESENCOFRADO NORMAL PARA MUROS Los encofrados deberán ajustarse a la configuración, líneas de elevación y dimensiones que tendrá el elemento de concreto por vaciar y según lo indiquen los planos. Los encofrados serán diseñados y construidos de tal forma que resistan plenamente el empuje del concreto al momento del llenado, sin deformarse y ser capaces de resistir las cargas previstas durante el período de fraguado. El material de los encofrados podrá ser de metal, madera o ambos, en el caso de usar madera la superficie en contacto con el concreto deberá estar acabada y cepillada para lograr un Acabado Normal, en otro caso de usar paneles de Triplay de 1 8 mm de espesor la superficie en contacto con el concreto debe estar tratada para lograr un Acabado Caravista. Tanto las uniones como las piezas que constituyen el encofrado deberán poseer la resistencia y rigidez necesarias para soportar los esfuerzos estáticos y dinámicos (peso propio, circulación de personal vibrado del concreto y eventualmente sismos o vientos) que se generen durante y después del vaciado, sin llegar a deformarse, debiendo evitar además la pérdida de concreto por las juntas. El encofrado debe ser construido de tal modo que las superficies del concreto estén de acuerdo a los límites de variación indicados en la siguiente relación de tolerancia admisibles.

La variación en las dimensiones de la sección transversal de las losas, muros, columnas y estructuras similares serán de 6 mm a + 12 mm. * Variación de la vertical en las superficies de columnas, muros y otras estructuras similares. • • •

Hasta una altura de 3 m. 6 mm. Hasta una altura de 6 m. 10 mm. Variación a niveles o gradientes indicados en los planos para piso, techo, vigas y estructuras similares. • En cualquier nivel o en 6 m. máximo 3 mm. PROCEDIMIENTO Encofrado Las planchas de madera que conforman el encofrado se humedecerán lo suficiente para ambas caras antes de proceder al vaciado del concreto para evitar la absorción del agua contenida en la mezcla. Las superficies de los encofrados en contacto con el concreto deberán ser limpiadas convenientemente a fin de eliminar sustancias extraídas como concreto secas, lechada, etc. Asimismo, dicha superficie deberá ser untada con aceite emulsionado de tipo comercial o con aceite normal parafínico refinado u otro aditivo de probada calidad y aprobado por la Supervisión, para las superficies visibles se exigirá un acabado tipo Caravista. Este tratamiento se deberá aplicar veinticuatro (24) horas antes como mínimo, de dar inicio al vaciado teniendo en cuenta que la cantidad de aceite y/o aditivo desmoldante a aplicarse deberá ser absorbida totalmente por la madera a fin de no manchar la superficie de concreto. En el caso del aditivo aplicar según la recomendación del fabricante. Los amarres, ganchos y anclajes que unen entre si las planchas de¡ encofrado deberán tener la propiedad de dejar en las superficies de¡ concreto, agujeros del menor diámetro posible. Los tirantes de anclaje dispuestos para someter las formas deberán permanecer sumergidos en el concreto y han de ser cortados a una distancia no menor al doble del diámetro o de su dimensión mínima en el interior de¡ concreto, desde la superficie externa, salvo en acabado que no van a quedar a la vista en donde se podrán cortar en la superficie externa del concreto. Luego se deberán resanar la superficie, de manera que el fierro quede cubierto de concreto. Todos los encofrados, para volver a ser usados, no deberán presentar alabeo, ni deformaciones y deberán ser limpiados con sumo cuidado antes de volver a ser colocados. La partida está referida tanto para encofrado vertical y horizontal.

Desencofrado El desencofrado se hará retirando las formas cuidadosamente para evitar daños en la superficie de las estructuras. La remoción del encofrado se hará después que el concreto haya adquirido la consistencia necesaria para soportar su peso propio y las cargas vivas a que pudiera estar sujeto, los tiempos de desencofrado se reducirán en lo posible a fin de no dilatar demasiado los procesos de acabado y reparación de la superficie del concreto. En general los encofrados deberán permanecer colocados los tiempos mínimos que se especifiquen salvo indicación expresa en los planos y/o de la Supervisión. Costado de vigas muros que no sostengan terreno 24 hrs Muros que sostengan terreno 7 días Muros y columnas sin carga 3 días Losas 14 días Fondo de vigas 21 días

UNIDAD DE MEDIDA Esta partida será medida en m2 (metro cuadrado) de área de contacto con el concreto, medido de acuerdo a los planos y aprobados por el Supervisor. FORMA DE PAGO El pago será por metro cuadrado de acuerdo a la definición anterior, al costo unitario de Contrato, el cual constituirá los costos de mano de obra, materiales, herramientas y equipos necesarios para habilitar, manipular, montaje, desmontaje, desmoldeadores necesarios para un acabado Caravista en las superficies expuestas y limpieza del encofrado. Incluye encofrado vertical o encofrado horizontal. La apartida está referido a encofrado y desencofrado tanto vertical y horizontal.

03.02. CONCRETO f´c=175 Kg/cm2 Alcance del Trabajo Comprende el suministro de mano de obra, herramienta, materiales y equipo necesario para la preparación y transporte, vaciado, acabado y curado del concreto f’c=175 kg/cm2 y f’c = 210 kg/cm2 el cual será utilizado para el vaciado del canal y sus obras de arte, así como en los lugares en donde indique los planos respectivos. El Ejecutor tendrá que mandar a diseñar al laboratorio el concreto requerido con el material propio de la zona para garantizar la resistencia, durabilidad, impermeabilidad de la estructura; en coordinación con el Ing. Residente y el Ing. Supervisor. El supervisor podrá variar las proporciones de mezcla de tiempo en tiempo, según sea necesario de acuerdo a las condiciones existentes.

Para un mejor resultado del concreto se recomienda tomar las consideraciones anteriormente descritas. Medición y Pago La unidad de medida, es el metro cúbico (m3) y se valorizará con el metrado obtenido en el campo aprobados por el Supervisor. Se pagará de acuerdo al precio unitario de la partida indicada en el Presupuesto.

03.03. CONCRETO CICLOPEO f'c=175 kg/cm2 + 30% DE P.G. Se empleará el equipo necesario y con la capacidad adecuada para producir el concreto de acuerdo al programa constructivo propuesto. Este equipo será respaldado por otro a fin de garantizar el cumplimiento del programa en el caso de reparaciones o fallas del equipo base. Para el diseño de la mezcla del concreto, se deberá tomar en consideración la resistencia del proyecto de 175 kg/cm2, revenimiento del orden de 10 centímetros y tamaño máximo de agregado de1 ½”. Para la fabricación del concreto la dosificación deberá hacerse por peso, utilizando agregados debidamente clasificados y empleando cemento portland tipo 1. Las rocas que se empleen deberán presentar superficies limpias y humedecidas, debiendo ser sanas, por lo tanto deberán eliminarse los fragmentos que demuestren intemperización. COLOCACION. El vaciado del concreto base deberá realizarse en forma continua y por capas de altura de 45 centímetros, la cual debe ser adecuada de acuerdo con los resultados que se vaya obteniendo. La roca incorporada presentara salientes del orden de los 15 a 20 centímetros con objeto de proporcionar una correcta adherencia con la capa subsecuente. La superficie del concreto, al concluirse cada colado debe protegerse para evitar que el concreto pierda humedad, manteniendo húmeda la superficie hasta recibir el colado de la primer capa del recinto superior. Para los recintos que se formen, una vez colados los primeros, la superficie deberá tratada para recibir el colado de la primera capa, tal tratamiento consistirá de una limpieza enérgica con chiflón y humedecimiento de la superficie. La roca que se incorpore al concreto podrá ser manejada con maquinaria, cuyo porcentaje será de 30% del volumen de concreto colocado, será medido a través de tamices adecuados para garantizar la colocación de piedra mediana. INCORPORACION DE ROCA. La roca que se incorpore al concreto base para formar el concreto ciclópeo, se obtendrá seleccionando de los boleos del acarreo del río.

HILADAS DE CONCRETO CICLOPEO. El concreto ciclópeo se colocara en hiladas de 0.4 metros (cero punto cinco) metros por un ancho de 5.0 metros (cinco punto cero) en el sentido transversal a la corriente y en longitud de acuerdo a lo socavado en el sentido de esta, la dimensión máxima del recinto jamás excederá la longitud máxima en la que la maquinaria y equipo puedan depositar roca y concreto de manera segura y eficiente. MEDICION Y PAGO. El concreto ciclópeo se medirá en metros cúbicos (m3)

04. CONCRETO ARMADO 04.01. CONCRETO f'c=280 kg/cm2 Comprende el suministro de mano de obra, herramienta, materiales y equipo necesario para la preparación y transporte, vaciado, acabado y curado del concreto f’c = 280 kg/cm2 el cual será utilizado para el vaciado de muros y columnas, así como en los lugares en donde indique los planos respectivos. El Ejecutor tendrá que mandar a diseñar al laboratorio el concreto requerido con el material propio de la zona para garantizar la resistencia, durabilidad, impermeabilidad de la estructura; en coordinación con el Ing. Residente y el Ing. Supervisor. El supervisor podrá variar las proporciones de mezcla de tiempo en tiempo, según sea necesario de acuerdo a las condiciones existentes. Para un mejor resultado del concreto se recomienda tomar las consideraciones anteriormente descritas. MEDICIÓN Y PAGO La unidad de medida, es el metro cúbico (m3) y se valorizará con el metrado obtenido en el campo aprobados por el Supervisor. Se pagará de acuerdo al precio unitario de la partida indicada en el Presupuesto.

04.02. ACERO DE REFUERZO fy=4,200 kg/cm2 El Ejecutor debe suministrar, detallar, fabricar e instalar todas las varillas de acero de refuerzo, necesarias para completar las estructuras de concreto armado según se muestran en los planos correspondientes. Todas las varillas de refuerzo, se conformarán a los requisitos de las Especificaciones ASTM A-615 para varillas de acero Grado 60. El acero deberá tener un límite de fluencia de 4,200 kg/cm2 como mínimo. PROCEDIMIENTO Las varillas de acero de refuerzo serán habilitadas en taller en el campo. El Ejecutor será el total y único responsable del detalle, suministro, doblado y colocación de todo el acero de refuerzo.

Antes de efectuar la colocación de varillas, la superficie de las mismas será limpiada de todo óxido, escamas, suciedad, grasa y cualquier otra sustancia ajena que en la opinión del Supervisor sea rechazable. El óxido grueso en forma de escamas, será removido por escobillado con crudos u otro tratamiento equivalente. Todos los detalles y habilitación, serán efectuados de acuerdo a la Especificación ACI-315 “Manual de prácticas normales para detallar estructuras de concreto”. Todos los anclajes y traslapes de las varillas, satisfacen los requisitos de la Especificación ACI-318 “Requisitos del Código de edificación para concreto armado” De requerirse soldadura, el Ejecutor deberá solicitar la autorización del Supervisor. Los trabajos de soldadura deberán cumplir con las normas AWS D 10 “Code for Welding in Building Construction” y AWS D 12.1 “Recommended Practice for Welding Reinforcing Steel, Metal Insert and Connentions in Reinforced Construction” de la American Welding Society. El Supervisor podrá solicitar al Ejecutor que proporcione, corte, doble y coloque una cantidad razonable de acero adicional y misceláneo, según encuentre necesario para completar las estructuras, siempre y cuando las modificaciones sean introducidas en los planos, diseños y/o cuaderno de obra. Las varillas de refuerzo serán colocadas con precisión y firmemente aseguradas en su posición, de modo que no sean desplazadas durante el vaciado del concreto. Antes y después de su colocación, las varillas de refuerzo se mantendrán en buenas condiciones de limpieza, hasta que queden totalmente empotradas en el concreto. TOLERANCIAS Las tolerancias de fabricación para acero de refuerzo serán los siguientes: a)

b)

Las varillas utilizadas para refuerzo de concreto cumplirán los siguientes requisitos para tolerancias de fabricación: • Longitud de corte : + 1” • Estribo, espirales y soportes : + 1 ½” • Dobleces : + 1 ½” Las varillas serán colocadas siguiendo las siguientes tolerancias: • • •

c)

Cobertura de concreto a la superficie: + 1” Espaciamiento mínimo entre varillas: + 1” Varillas superiores en losas y vigas Miembros de 8” de profundidad o menos: + ¼” Miembros de más de 8” pero inferiores a 24” de profundidad: + ½” • Miembros de más de 24” profundidad : + 1” Las varillas pueden moverse según sea necesario, para evitar interferencias con otras varillas de refuerzo de acero, conductos, o materiales empotrados.

Si las varillas, se mueven más de 2 diámetros o lo suficiente para exceder estas tolerancias, el resultado de ubicación de varillas estará sujeto a la aprobación del Supervisor. UNIDAD DE MEDIDA El acero de refuerzo se medirá en kilogramos (kg) con aproximación de 02 decimales, para tal efecto se determinara la longitud neta del acero de refuerzo y luego transformada a peso. FORMA DE PAGO La forma de pago será por kilogramos (kg), con el correspondiente precio unitario de la partida contratada la que incluye los costos de mano de obra, insumos, equipo, herramientas manuales y otros necesarios para realizar dicha partida.

05. CARPINTERIA METALICA 05.01. SUMINISTRO Y MONTAJE DE COMPUERTA PLANA DE 0.80 X 1.20, ¼” C/ANGULOS Φ 1/4”X3/4” El trabajo incluido en este rubro consistirá en el suministro y colocación de una compuerta metálica para el canal especificado en los planos respectivos. La compuerta será de plancha metálica de acero fundido de 3/16” de espesor, con sus respectivos mecanismos de izaje, los modelos a usarse cumplirán con las dimensiones, condiciones y requerimientos a que serán sometidos dentro de la obra Los materiales de acero estructural u otros relativos a los mismos para las compuertas, deberán sujetarse a los especificados en los planos o serán similares a los mismos MATERIAL Perfiles laminado en caliente Acero estructural Plancha de acero Fundación de acero Pernos de anclaje Estructural Pasador de acero inoxidable| Presión del pasador (Camiseta de Bronce) Pernos en gral Soldadura

ESPECIFICACION ASTM A-36 ASTM A-327 ASTM A-490 ASTM A-36 TIPO 416 ASTM A-193 AWS D1.1 ASTM para iron & Steel Arc Weiding Electrodes

MÉTODO DE MEDICIÓN Se considera la adquisición y la colocación de la estructura metálica su medición es la Unidad (Und) FORMA DE PAGO El pago del suministro y la colocación donde se incluirá el precio de la estructura metálica como su colocación utilizando las herramientas, mano de obra.

05.02. SUMINISTRO Y MONTAJE DE COMPUERTA PLANA DE 1.00 X 1.20, ¼” C/ANGULOS Φ 1/4”X3/4” Ver Item 05.01

05.03. FABRICACION, COLOCACION DE BARANDAS METALICAS (INC PINTURA DESCRIPCIÓN Bajo esta partida, el Contratista deberá efectuar convenientemente la construcción de postes de acero y pasamanos de tubos de fierro, y que es parte integrante de la superestructura del puente, en conformidad con la ubicación y detalles indicados en los planos. MATERIALES Los perfiles y planchas serán con acero de calidad ASTM A36 y se utilizaran electrodos AWS E6018. El acabado será con pintura anticorrosiva epóxica y dos manos de pintura esmalte epóxica. EJECUCIÓN En general la fabricación de las barandas deberá cumplir con las especificaciones de fabricación de estructuras metálicas. Las barandas de los puentes deben ser construidas de acuerdo con las trazas y rasantes indicadas en los planos y no deberá reflejar ningún desnivel en la estructura. Todos los postes de la baranda deben ser verticales. Previo al proceso de pintado deberá someterse a las barandas a un proceso de limpieza mediante arenado comercial. Las barandas serán colocadas y pintadas, teniendo el cuidado de pintar con una base de wash primer toda superficie galvanizada para su acabado final. Para el caso de los postes de acero estructural, se le aplicará pintura zinc Rich Inorgánico, cuidando en todo momento que área de la soldadura entre tubos y postes esté perfectamente acabada. En todas sus etapas de pintado se debe contar con la aprobación de la Supervisión, quien evaluará el material a ser usado, así como de la aprobación del acabado del mismo a la culminación de su instalación. Esto no elimina la responsabilidad del contratista sobre estos trabajos siendo de su completa responsabilidad la culminación y entrega de los mismos en las condiciones que aquí se detallan.

Los postes se fijarán en unos parapetos o muros mediante pernos de anclaje de 5/8” y fijándolos luego con las tuercas, para lo cual el contratista deberá suministrar la plancha de acero inferior (debidamente pintada) mostrada en el plano de detalle de la baranda. MEDICIÓN La medición de las barandas del puente deberá efectuarse por metro lineal, en la ubicación, medidas, alineamientos, limpieza y revestimiento de pintura, según lo mostrado en los planos. PAGO Las cantidades medidas en la forma descrita, se pagarán por metro lineal al precio unitario del contrato; dicho pago incluirá la adquisición de las planchas de acero, tubos galvanizado, habilitación, soldadura, colocación y pintura, además de los imprevistos necesarios para la correcta ejecución de los trabajos.

06. IMPACTO AMBIENTAL 06.01. LIMPIEZA Y RESTAURACION DE PATIO DE MAQUINAS Y CASETAS La adecuación y reposición del área intervenida debe ejecutarse luego del desmantelamiento del campamento. Las principales acciones a llevar a cabo son: eliminación de desechos, clausura de las letrinas y rellenos sanitarios, eliminación de pisos de concreto u de otro material utilizado, recuperación de la morfología del área y re vegetación, si fuera el caso. El algunos casos, puede existir la posibilidad de aparición de asentamientos humanos precarios alrededor de los campamentos; en tal sentido, se requiere de la aplicación de medidas para evitar dichos desarrollo poblacionales. En este caso se efectuarán las coordinaciones necesarias con la población y las autoridades de gobierno para impedir su localización en áreas aledañas a las que fueron previamente seleccionadas como campamentos para evitar el desarrollo probable de asentamientos poblacionales precarios en base a la localización de dichos campamentos. MEDICIÓN: La medida será por metro cuadrado. BASES DE PAGO: La cantidad medida en la forma indicada anteriormente, se pagará por el precio unitario del contrato.

06.02. SELLADO DE LETRINAS La adecuación y reposición del área intervenida debe ejecutarse luego del desmantelamiento del campamento. Las principales acciones a llevar a cabo son:

eliminación de desechos, clausura de las letrinas y rellenos sanitarios, eliminación de pisos de concreto u de otro material utilizado, recuperación de la morfología del área y re vegetación, si fuera el caso. El algunos casos, puede existir la posibilidad de aparición de asentamientos humanos precarios alrededor de los campamentos; en tal sentido, se requiere de la aplicación de medidas para evitar dichos desarrollo poblacionales. En este caso se efectuarán las coordinaciones necesarias con la población y las autoridades de gobierno para impedir su localización en áreas aledañas a las que fueron previamente seleccionadas como campamentos para evitar el desarrollo probable de asentamientos poblacionales precarios en base a la localización de dichos campamentos. MEDICIÓN: La medida será por unidad. BASES DE PAGO: La cantidad medida en la forma indicada anteriormente, se pagará por el precio unitario del contrato.

07. FLETE TERRESTRE 07.01. FLETE TERRESTRE Descripción del trabajo La partida comprende todo el traslado de materiales de construcción, herramientas, equipos y demás insumos desde la ciudad de Lima hasta la localidad de Chaclacayo. Unidad de medida La medición por este concepto será en forma global (GLB) por todos los materiales trasladados hacia obra y a todo costo. Forma de pago El pago se efectuará de acuerdo al traslado de los materiales hasta el campamento de obra. El importe total a pagar será el correspondiente a la partida.

3.11 Cronograma de ejecución de obra

3.12 Crongrama valirizado de obra PROYECTO

:"REHABILITACION BOCATOMA CASTRILLEJO, DISTRITO DE CHACLACAYO, PROVINCIA DE LIMA, DEPARTAMENTO DE LIMA"

PROPIETARIO

: AUTORIDAD PARA LA RECONSTRUCCION CON CAMBIOS

DEPARTAMENTO :LIMA

PROVINCIA :LIMA

DISTRITO :CHACLACAYO

LUGAR

HECHO POR :

REVISADO :

FECHA

Ing. J. Orlando Valverde Fernández

:SECTOR 2

:JULIO del 2018



ITEM

MES 1

MES 2

MES 3

Parcial (S/)

CART EL DE IDENT IFICACION DE LA OBRA DE 3.60 X 2.40 m

1,032.51

1.02

MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPO

1,975.76 1,975.76

3,951.52

1.03

CONST RUCCION DE CAMPAMENT O

3,140.55

3,140.55

1.04

DESVÍO DE RIO

2,160.00

1.05

T RAZO Y NIVELACION DURANT E LA OBRA

1,238.52

1.01

2 2.01

2.03

RELLENO COMPACT ADO MANUAL CON MAT ERIAL DE PREST AMO

2.04

REFINE Y NIVELACION EN T ERRENO NORMAL

2.05

EXCAVACION PARA CONFORMACION DE CIMIENT OS DE MUROS

2.08

RELLENO COMPACT ADO MANUAL- CON MAT ERIAL DE PROPIO

3.01

ENCOFRADO Y DESENCOFRADO NORMAL CONCRET O f'c=175 kg/cm2

3.01

CONCRET O CICLOPEO f'c=175 kg/cm2 + 30 % PG.

6,896.61 430.74

430.74 523.61

523.61 59.62

59.62

119.23

1,482.69

1,482.69 6,067.56

6,067.56

4,341.11 4,341.11 4,341.11 831.09

13,023.34

831.09

1,662.17

25,716.03 25,716.03

51,432.06

CONCRET O ARMADO

4.01

CONCRET O f 'c=280 kg/cm2

4.02

ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60

31,948.55 31,948.55

63,897.09

12,948.16 12,948.16 12,948.16

38,844.48

CARPINT ERIA MET ALICA

5.01

COMPUERT A MET ÁLICA T IPO IZAJE 1/4" x 1.20 x 0.80m

5.02

COMPUERT A MET ÁLICA T IPO IZAJE 1/4" x 1.20 x 0.70m

5.03

FABRICACION Y COLOCACION DE BARANDAS MET ALICAS

6

3,715.56

OBRAS DE CONCRET O SIMPLE

3.02

5

1,238.52

6,896.61

DESCOLMAT ACION DE CAUCE DE RIO EXCAVACION EN MAT ERIAL CONGLOMERADO A MANO

4

2,160.00 1,238.52

MOVIMIENT O DE T IERRAS

2.02

3

1,032.51

3,123.70

3,123.70 2,863.70

2,863.70 3,512.18

MIT IGACION AMBIENT AL

6.01

LIMPIEZA Y REST AURACION DE PAT IO DE MAQUINAS Y CASET AS

6.02

SELLADO DE LET RINAS

7

FLET E URBANO Y RUAL

7.01

FLET E URBANO Y RUAL

813.00

3.13 Planos a nivel constructivo Ver Anexos 11

2,879.84

5,510.30 5,510.30 11,659.12 10,884.58 6,896.61

COSTO DIRECTO

813.00 2,879.84

29,871.05

430.74

1,762.13 27,258.34 49,963.56 50,068.90 50,476.34 3,123.70 3,676.70 6,392.02 129,052.93

63,668.76

222,592.74 222,592.74

CAPITULO IV: CONCLUSIONES Y RECOMENDACIONES

4. CONCLUSIONES Y RECOMENDACIONES  





Para la protección de la bocatoma se esta proponiendo la contruccion de una defensa ribereña tipo enrocado. Para asegurar que el caudal de dotación infrese por la copuerta del canal de derivación se esta proponiendo la constrccion de un espigon de 15m de largo que ira empotrada en el enrocado. Para proteger la bocatoma de incrementos de nivel del rio Rimac, se esta proponiendo la construccion de muros de protección de una altura de 2.40m y en las compuertas tendrá una altura de 2.10m. Se recomienda que antes de realizar los trabajos de descolmatacion del cauce se debe realizar un levantameinto topográfico con los detalles necesarios

CAPITULO V: ANEXOS

5. Anexos

5.1 TOPOGRAFIA DEL AREA DE LAS OBRAS

5.2 ESTUDIO HIDROLOGICO

5.3 DISEÑO HIDRAULICO

5.4 GEOTECNIA PARA DISEÑO DE CIMENTACION

5.5 ANALISIS DE RIESGO DE DESASTRES

5.6 IDENTIFICACION DE LOS IMPACTOS AMBIENTALES

Related Documents

Memoria
November 2019 58
Memoria
June 2020 29
Memoria
May 2020 34
Memoria
October 2019 57
Memoria
November 2019 48

More Documents from ""